Construction research 2026-10-24: Epoch’s[1] 2026-05-20 observation documents remaining physical construction/installation for this named buildout. In Progress does not complete earlier operating buildings or future capacity. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget. Source quote: “Building 3 has cleared its land and is beginning construction.” Dated observation 2026-05-20; future trajectory rows and modeled costs are distinguished from this physical milestone.
有遗漏或错误吗?用你自己的话说明:能佐证此图钉的链接、不同的开始或结束日期及理由,或缺失、有误的信息。AI 会对照此图钉的来源进行核实,搜索更好的来源,并添加任何支持你说法的页面。图钉自身的来源仍然最重要。AI 也会查看图片:显示的是别的东西或显示效果差的图片会被移到后面或替换。
| 2027-06-30 | 根据当前的 PowerHouse 时间表,3 号楼预计将于 2027 年第一季度末完工。又增加了三个月的调试和服务器安装时间。 |
|---|
Epoch AI 卫星图像注释,按日期顺序排列。 · 来源
Physical-stage observation dated 2026-05-20. Campus buildout remains under construction; already operating buildings do not complete the remaining work. Forecast operational dates retain the directory’s uncertainty and do not establish actual completion.
“Building 3 has cleared its land and is beginning construction.”
Epoch’s dated 2026-05-20 assessment: Building 3 has cleared its land and is beginning construction. Campus buildout remains under construction; already operating buildings do not complete the remaining work.
“Building 3 has cleared its land and is beginning construction.”
Epoch estimates AI hardware: Nvidia H100 and Nvidia B200 chips. Chip fit-out is directory research, not operator-certified inventory.
“We estimate that it uses Nvidia H100 and Nvidia B200 chips.”
Epoch dated observation: Conversion starts at CTP-01 (Building 1).
“Conversion starts at CTP-01 (Building 1).”
Epoch dated observation: Based on satellite imagery, Building 3 has cleared its land and is…
“Based on satellite imagery, Building 3 has cleared its land and is beginning construction.”
原标题: CoreWeave Chester VA AI Data Center Buildout
Epoch 2026 年 5 月 20 日的观察记录了这个指定扩建项目的剩余物理施工/安装情况。 “进行中”并不完成早期运营的建筑或未来的容量。 功率和加速器数量仍然是 Epoch 的估计值,而不是运营商认证的评级。 建模的 2025 美元资本成本包括计算硬件,而不是源本地建设预算。
Epoch AI 通过带注释的卫星足迹(9 个物理部分)跟踪超大规模前沿 AI 训练和推理园区。