Construction research 2026-10-24: Epoch’s[1] 2026-05-02 observation documents remaining physical construction/installation for this named buildout. In Progress does not complete earlier operating buildings or future capacity. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget. Source quote: “Buildings 1 and 2 cooling install continues” Dated observation 2026-05-02; future trajectory rows and modeled costs are distinguished from this physical milestone.
Five-building QTS Eagle Mountain campus.[1]
有遗漏或错误吗?用你自己的话说明:能佐证此图钉的链接、不同的开始或结束日期及理由,或缺失、有误的信息。AI 会对照此图钉的来源进行核实,搜索更好的来源,并添加任何支持你说法的页面。图钉自身的来源仍然最重要。AI 也会查看图片:显示的是别的东西或显示效果差的图片会被移到后面或替换。
| 2027-07-01 |
|---|
| 我们预计 3 号楼将于 2027 年下半年全面投入运营,其时间与 1 号楼和 2 号楼类似,从土地清理到投入运营也需 14 个月。 |
Epoch AI 卫星图像注释,按日期顺序排列。 · 来源
Physical-stage observation dated 2026-05-02. Campus buildout remains under construction; already operating buildings do not complete the remaining work. Forecast operational dates retain the directory’s uncertainty and do not establish actual completion.
“Buildings 1 and 2 cooling install continues”
Epoch’s dated 2026-05-02 assessment: Buildings 1 and 2 cooling install continues Campus buildout remains under construction; already operating buildings do not complete the remaining work.
“Buildings 1 and 2 cooling install continues”
AI data-center compute infrastructure. Hardware inventory remains unpublished or not verified in this project assessment.
“AI data center”
Epoch dated observation: First signs of site preparation show up on satellite imagery.
“First signs of site preparation show up on satellite imagery.”
Epoch dated observation: Building 1 roof finished.
“Building 1 roof finished.”
原标题: QTS Eagle Mountain AI Data Center Buildout
Epoch 的 2026 年 5 月 2 日观察记录了这个指定扩建项目的剩余物理施工/安装情况。 “进行中”并不完成早期运营的建筑或未来的容量。 功率和加速器数量仍然是 Epoch 的估计值,而不是运营商认证的评级。 建模的 2025 美元资本成本包括计算硬件,而不是源本地建设预算。
Epoch AI 通过带注释的卫星足迹(7 个物理部分)跟踪超大规模前沿 AI 训练和推理园区。