Chornobyl NPP Accepts Novarka's New Safe Confinement Into Operation
- On 8 November 2017 the Enclosing Perimeter of the New Safe Confinement (NSC) was accepted into operation at Chornobyl NPP; NOVARKA handed over the NSC on 10 July 2019 and trial operation began 24 April 2020[2]
- The arch has a 257 m span, 108 m height and 162 m length; the contract with NOVARKA (VINCI and Bouygues) was signed 10 August 2007[2][3]
- It was slid 327 m into position over Reactor 4's 1986 shelter, completed 29 November 2016[2][3]
- It is the largest moveable land-based structure ever built, weighing 36,000 tonnes equipped, with a 100-year lifetime[3]
- Cost was EUR 1.5 billion, funded by 45 donor countries and Ukraine through the EBRD-managed Chernobyl Shelter Fund[2][3]
- Gamma radiation in the former arch construction zone fell about 10 times, and it enables dismantling of unstable structures and retrieval of radioactive material[2]
References 390% CONFIDENCE
The first entry is always the pin's source. Overall confidence is a weighted average of how firmly each reference supports the start and end times used above; a reference counts half as much for every 180 days older than the newest.
- [1]90%youtube.com/watch?v=fScXvnDpb-wyoutube.com· Posted Sep 22, 2026· Starts Nov 8, 2017· 100% of score
Ukraine's Chornobyl NPP states it accepted the New Safe Confinement's Enclosing Perimeter into operation on 8 November 2017 (chnpp.gov.ua[2]).
- [2]95%Project "New Safe Confinement Construction"chnpp.gov.ua· Published Nov 8, 2017· Starts Nov 8, 2017 ✓· Ends Nov 8, 2017 ✓· 0% of score
Chornobyl NPP's own project page states it accepted the NSC's Enclosing Perimeter into operation on 8 November 2017.[1]
- [3]85%Unique engineering feat concluded as Chernobyl arch has reached resting placeebrd.com· Published Nov 29, 2016· Starts Nov 14, 2016· Ends Nov 29, 2016· 0% of score
The EBRD, which financed the project, confirms the arch was skidded into its final position over 14-29 November 2016.
Suggest a correction
Something missing or wrong? Say it in your own words: a link that backs this pin up, a different start or end date and why, or a fact it lacks or gets wrong. The AI checks it against this pin's sources, searches for better ones, and adds any page that backs you up. The pin's own sources still count most.