Babcock & Wilcox Gets Go-Ahead on $2.4B Base Electron Power Plant
- On 4 March 2026 Babcock & Wilcox received full notice to proceed on a $2.4 billion design-build agreement with Base Electron, an independent power producer backed by Applied Digital, to deliver 1.2 GW of new generation capacity[1][6].
- The agreement itself is dated 26 February 2026; B&W undertakes to keep the contract price within $2.4 billion and guarantees each unit's commercial-operation-readiness date[3][4].
- The project is four 300 MW natural gas-fired boilers with steam turbine generator systems; B&W will engineer, procure and construct it, and Siemens Energy was formally released to design and supply the turbine sets[1][6].
- The power is to supply Applied Digital AI Factory campuses under separate power supply agreements, and Base Electron is weighing an option for another 1.2 GW[1][6].
- Applied Digital guarantees Base Electron's obligations to B&W and holds about 10% of Base Electron, whose owners include some Applied Digital officers and directors[4].
- The release named no site; B&W's August 2026 investor deck put the project near Center, North Dakota, where this pin is placed[2]; Industrial Info had instead linked the B&W system to Applied Digital's Polaris Forge campus at Ellendale[5].
References 687% CONFIDENCE
The first entry is always the pin's source. Overall confidence is a weighted average of how firmly each reference supports the start and end times used above; a reference counts half as much for every 180 days older than the newest.
- [1]90%babcock.com/home/about/corporate/news/babcock-and-wilcox-receives-full-notice-to-proceed-on-24-billion-power-generation-project-for-base-electron-to-supply-power-to-applied-digital-ai-factory-campusesbabcock.com· Posted Sep 23, 2026· Starts Mar 4, 2026 ✓· 26% of score
Stated as done, per babcock.com: "(AKRON, Ohio - March 4, 2026) - Babcock & Wilcox ... announced today that it has received full notice to proceed on a $2.4 billion design-build agreement"; the Business Wire copy on Yahoo Finance is timestamped 11:30 UTC.
- [2]90%Babcock & Wilcox investor overview, August 2026 (8-K exhibit)sec.gov· Published Aug 10, 2026· 22% of score
B&W's filed August 2026 presentation: the $2.4B, 1.2 GW Base Electron project "will be located near Center, North Dakota" and its Conditional Use Permit was submitted in August 2026, with potential for another 1.2 GW.[1]
- [3]90%Design-Build Agreement between Base Electron, Inc. and The Babcock & Wilcox Company (10-Q Exhibit 10.3)sec.gov· Published May 11, 2026· 15% of score
The agreement itself, dated 26 February 2026: Base Electron is developing a 1,200 MW generation facility; B&W commits to keep the Contract Price within $2,400,000,000 and guarantees each unit's Commercial Operation Readiness date (the schedule is redacted).[1]
- [4]85%Applied Digital Form 10-Q for the quarter ended February 28, 2026sec.gov· Published Apr 8, 2026· 13% of score
Applied Digital's 10-Q: the 4 November 2025 B&W warrant agreement, the 26 February 2026 Design-Build Agreement between Base Electron and B&W, Applied Digital's guarantee of Base Electron's obligations and its ~10% stake in Base Electron.[1]
- [5]75%Babcock & Wilcox Signs $2.4 Billion Deal to Support Applied Digital Data Centersindustrialinfo.com· Published Mar 17, 2026· 12% of score
Industrial Info tracks Applied Digital campuses in Louisiana, Iowa and the Dakotas and links a North Dakota data center with the B&W power system; it names Polaris Forge 1 at Ellendale, not the site B&W later named near Center.
Suggest a correction
Something missing or wrong? Say it in your own words: a link that backs this pin up, a different start or end date and why, or a fact it lacks or gets wrong. The AI checks it against this pin's sources, searches for better ones, and adds any page that backs you up. The pin's own sources still count most.