原标题: S-Oil's Shaheen Petrochemical Complex Starts Commercial Operation
第一项始终是图钉的来源。总体可信度是各份资料对上方所用开始和结束时间支持程度的加权平均;资料每比最新的一份旧 180 天,权重减半。
已推迟,据 iusm.co.kr:S-Oil 在 2026 年 8 月 3 日的电话会上表示,在预调试和开车之后,“目标于 2027 年初实现商业运营”;KBS(2026 年 2 月)给出的目标为 2027 年 1 月,因此取该月最后一天。
S-Oil's Q1 2026 call: mechanical completion end of June, commissioning in the second half, commercial operation early next year.[1]
Hankyung (via Nate): 95% progress, June mechanical completion, TC2C yields over 70%, 150 MW LNG power plant, and the Hormuz closure's effect on crude supply.
KBS News report: 94% complete, all equipment installed by end of June, commissioning in the second half and commercial operation targeted for January 2027.[1]
Site visit: 85% complete on 15 Oct 2025, commercial operations scheduled for the second half of 2026 (the original date), 9.26 trillion won, TC2C and cracker specs, Aramco as largest shareholder.[1]