这个标记会跟进新闻:它显示目前已知的情况,这里列出改了什么以及起因。
已编辑由 @ThePinGang
之前
IAEA’s 2024 Climate Change and Nuclear Power report identifies US$4 billion expected total cost for the Natrium demonstration project, separately from the US$2 billion DOE contribution. It describes one 345 MWe net reactor at Kemmerer. This is a dated published project estimate; it is not represented as a refreshed 2026 fixed-price budget.
IAEA’s 2024 Climate Change and Nuclear Power report identifies US$4 billion expected total cost for the Natrium demonstration project, separately from the US$2 billion DOE contribution. It describes one 345 MWe net reactor at Kemmerer. This is a dated published project estimate; it is not represented as a refreshed 2026 fixed-price budget. Natrium — Kemmerer Unit 1: 345 MW generating project rating. 345 MWe net continuous reactor output; storage-assisted peak excluded
TerraPower April 23, 2026 confirms official plant construction following the construction permit. Non-nuclear site support construction started June 2024. Reactor output is 345 MWe; storage-assisted 500 MW peak output is not additional continuous generating capacity.
Retained only with documented physical construction, commissioning or 2025–2026 opening and published project-specific costs and electrical output. Costs use the published scope and currency; no benchmark estimates or currency conversions. MW is power capacity, not annual electricity production. Expected annual energy, where given, is a forecast. The map point is a reported plant/project location and may be approximate. Matching inventory views and excluded expansion proposals are not additive capacity.
已编辑由 @ThePinGang
之前
之前
TerraPower announced the start of construction on Kemmerer Unit 1 on April 23, 2026 after receiving the NRC construction permit. Natrium’s reactor rating is 345 MW; the storage-assisted peak output is a different metric and must not be represented as the continuous reactor capacity.
Operator project page identifies Kemmerer as under construction. EPC contracting changes and schedule implications need a later sourced revisit.
GEM August 2026 snapshot: under construction. 345 MW sum of published phase ratings (ratings may mix solar DC/AC). Technologies: Nuclear.
Compare phase coverage and AC/DC, nameplate and net ratings before combining source figures. This inventory view is not extra capacity to add to the existing project total.
EIA August 2026 snapshot: approvals pending. 500 MW nameplate across 1 new/recent generating units. Technologies: Nuclear.
Compare phase coverage and AC/DC, nameplate and net ratings before combining source figures. This inventory view is not extra capacity to add to the existing project total.
Additional source view; compare phase coverage and rating conventions before combining figures.
Additional source view; compare phase coverage and rating conventions before combining figures.
已编辑由 @ThePinGang
之前
TerraPower announced the start of construction on Kemmerer Unit 1 on April 23, 2026 after receiving the NRC construction permit. Natrium’s reactor rating is 345 MW; the storage-assisted peak output is a different metric and must not be represented as the continuous reactor capacity.
Operator project page identifies Kemmerer as under construction. EPC contracting changes and schedule implications need a later sourced revisit.
GEM August 2026 snapshot: under construction. 345 MW sum of published phase ratings (ratings may mix solar DC/AC). Technologies: Nuclear.
Compare phase coverage and AC/DC, nameplate and net ratings before combining source figures. This inventory view is not extra capacity to add to the existing project total.
EIA August 2026 snapshot: approvals pending. 500 MW nameplate across 1 new/recent generating units. Technologies: Nuclear.
Compare phase coverage and AC/DC, nameplate and net ratings before combining source figures. This inventory view is not extra capacity to add to the existing project total.
Additional source view; compare phase coverage and rating conventions before combining figures.
已编辑由 @ThePinGang
之前
TerraPower announced the start of construction on Kemmerer Unit 1 on April 23, 2026 after receiving the NRC construction permit. Natrium’s reactor rating is 345 MW; the storage-assisted peak output is a different metric and must not be represented as the continuous reactor capacity.
Operator project page identifies Kemmerer as under construction. EPC contracting changes and schedule implications need a later sourced revisit.
GEM August 2026 snapshot: under construction. 345 MW sum of published phase ratings (ratings may mix solar DC/AC). Technologies: Nuclear.
Compare phase coverage and AC/DC, nameplate and net ratings before combining source figures. This inventory view is not extra capacity to add to the existing project total.
EIA August 2026 snapshot: approvals pending. 500 MW nameplate across 1 new/recent generating units. Technologies: Nuclear.
Compare phase coverage and AC/DC, nameplate and net ratings before combining source figures. This inventory view is not extra capacity to add to the existing project total.
已编辑由 @ThePinGang
之前
GEM August 2026 snapshot: under construction. 345 MW sum of published phase ratings (ratings may mix solar DC/AC). Technologies: Nuclear.
Compare phase coverage and AC/DC, nameplate and net ratings before combining source figures. This inventory view is not extra capacity to add to the existing project total.
EIA August 2026 snapshot: approvals pending. 500 MW nameplate across 1 new/recent generating units. Technologies: Nuclear.
Compare phase coverage and AC/DC, nameplate and net ratings before combining source figures. This inventory view is not extra capacity to add to the existing project total.
已编辑由 @ThePinGang
之前
GEM August 2026 snapshot: under construction. 345 MW sum of published phase ratings (ratings may mix solar DC/AC). Technologies: Nuclear.
Compare phase coverage and AC/DC, nameplate and net ratings before combining source figures. This inventory view is not extra capacity to add to the existing project total.
已编辑由 @ThePinGang
之前
这些是读者照片,与图钉带来源的媒体分开显示。
第一项始终是图钉的来源。总体可信度是各份资料对上方所用开始和结束时间支持程度的加权平均;资料每比最新的一份旧 180 天,权重减半。
有记录的实体里程碑或带日期的进展/报告节点。期末日期仅代表所报告的月份/季度,不会虚构确切的投运日期。来源中的估计值均已标注,不视为已确认的未来开业日期。
IAEA’s 2024 Climate Change and Nuclear Power report identifies US$4 billion expected total cost for the Natrium demonstration project, separately from the US$2 billion DOE contribution. It describes one 345 MWe net reactor at Kemmerer. This is a dated published project estimate; it is not represented as a refreshed 2026 fixed-price budget. Natrium — Kemmerer Unit 1: 345 MW generating project rating. 345 MWe net continuous reactor output; storage-assisted peak excluded
有遗漏或错误吗?用你自己的话说明:能佐证此图钉的链接、不同的开始或结束日期及理由,或缺失、有误的信息。AI 会对照此图钉的来源进行核实,搜索更好的来源,并添加任何支持你说法的页面。图钉自身的来源仍然最重要。AI 也会查看图片:显示的是别的东西或显示效果差的图片会被移到后面或替换。
原标题: Natrium — Kemmerer Unit 1 — under construction
国际原子能机构(IAEA)2024年的《Climate Change and Nuclear Power》报告称,Natrium示范项目预计总成本为40亿美元,与美国能源部(DOE)的20亿美元出资分开计算。报告描述凯默勒为一座净功率345 MWe的反应堆。这是带日期的已公布项目估算,并非2026年更新后的固定价格预算。[1][2]
国际原子能机构(IAEA)2024年的《Climate Change and Nuclear Power》报告称,Natrium示范项目预计总成本为40亿美元,与美国能源部(DOE)的20亿美元出资分开计算。报告描述凯默勒为一座净功率345 MWe的反应堆。这是带日期的已公布项目估算,并非2026年更新后的固定价格预算。Natrium——凯默勒1号机组:发电项目额定功率345 MW。反应堆连续净输出345 MWe;不含储能辅助的峰值[2]
TerraPower于2026年4月23日确认,在获得建造许可后电厂正式开工建设。厂址的非核支持设施建设已于2024年6月开始。反应堆输出功率为345 MWe;储能辅助的500 MW峰值输出并非额外的连续发电容量。[1]
仅保留有实体施工、调试或2025–2026年投运记录,且已公布项目专属成本和电力输出的项目。成本采用已公布的范围和货币;不使用基准估算或货币换算。MW为功率容量,而非年发电量。如有预期年发电量,则为预测值。地图上的点为所报告的电厂/项目位置,可能为大致位置。匹配的清单视图和被排除的扩建提案不属于可叠加的容量。
凯默勒1号机组开工活动照片,随TerraPower在美国核管会(NRC)颁发建造许可后于2026年4月23日发布的公告提供。这是活动照片,并非已建成的反应堆。图片来源:TerraPower;未具名个人摄影师。来源与图库;原始媒体。