Baltic Power[3][5] monopile installation image supplied with ORLEN’s February 2026 foundations-complete announcement.
Published project-specific cost for Baltic Power[5]: EUR 4.05e+09. Basis: Published project capex including insurance, excluding the separately described financing/reserve components. Published electric generating project rating for Baltic Power: 1140 MW. Basis: 76 operator-reported turbines × 15 MW; corroborated by inventory rating.
Northland Q2 2026 update confirms Baltic Power[3][5] first power, 61 of 76 turbines installed, 15 generating and construction/commissioning ongoing. Full commercial operations remain a second-half 2026 target; costs are aligned with original expectations.
Operator forecasts 4,000 GWh yearly electricity production; this is expected annual energy, distinct from rated MW.[1]
有遗漏或错误吗?用你自己的话说明:能佐证此图钉的链接、不同的开始或结束日期及理由,或缺失、有误的信息。AI 会对照此图钉的来源进行核实,搜索更好的来源,并添加任何支持你说法的页面。图钉自身的来源仍然最重要。AI 也会查看图片:显示的是别的东西或显示效果差的图片会被移到后面或替换。
原标题: Baltic Power — partly operational / under construction
Baltic Power公布的资本支出(含保险)约为40.5亿欧元,纳入总预算约47.3亿欧元之内。较大的总预算还包括融资成本和储备金;44亿欧元的信贷方案不计入建设成本。该发电项目共有76台单机15 MW的风机,合计1,140 MW;在8月清单中被列为在建。[3][4][5]
已公布的Baltic Power项目专项成本:EUR 4.05e+09。依据:已公布的项目资本支出(含保险),不含另行说明的融资和储备金部分。已公布的Baltic Power发电项目额定容量:1140 MW。依据:运营商报告的76台风机×15 MW;与清单中的额定容量相互印证。[3]
Northland 2026年第二季度更新确认Baltic Power已实现首次发电,76台风机中已安装61台,15台正在发电,建设和调试仍在进行。全面商业运营仍以2026年下半年为目标;成本与最初预期一致。[4]
运营商预测年发电量为4,000 GWh;这是预期的年度电量,不同于额定容量(MW)。[5]
仅保留有实体施工、调试或2025–2026年投运记录,且已公布项目专属成本和电力输出的项目。成本采用已公布的范围和货币;不使用基准估算或货币换算。MW为功率容量,而非年发电量。如有预期年发电量,则为预测值。地图上的点为所报告的电厂/项目位置,可能为大致位置。匹配的清单视图和被排除的扩建提案不属于可叠加的容量。