Stargate Milam County 'Freebird' Phase 1 Data Center Due for Completion
已排期日期确定性: 已排期已公布为计划日期来源对日期的表述有多确定:已确认、已排期、预估、已推迟或未核实。显示所有“已排期”的图钉可信度 75%总体可信度: 75%该图钉的来源和参考资料对其日期的支持程度。包括来源在内的 5 份资料对图钉开始和结束时间支持程度的加权平均;资料每比最新的一份旧 180 天,权重减半显示所有可信度不低于 75% 的图钉Scheduled: the Texas[1] Department of Licensing and Regulation filing lists "Completion Date: October 15, 2026" (start 20 Oct 2025); a filed date, not a confirmed handover.
Phase 1 of the SB Energy and OpenAI Freebird campus, a 548,950 sq ft, four-data-hall building in Burlington, Texas, has a filed completion date of 15 October 2026 and an estimated cost of $470 million.
$470M
1.00