Clēnera and Enlight reached a $2.6B financial close and commenced construction on the $3.05B, 1,211 MW solar and 4,000 MWh storage complex in Coconino County, Arizona.
Former Robena Mine site, Monongahela Township, Greene County, Pennsylvania, United States (approximate: Cleanview point on the Monongahela River)International Electric Power
International Electric Power(IEP)正在宾夕法尼亚州格林县莫农加希拉镇的Robena废弃煤矿上建设一座由两台燃气轮机组成的电力岛(IEP和县里称910 MW,合作伙伴Essential Utilities称944 MW),以吸引超大规模数据中心;第1期土地开发于2025年12月以8比1获批,目前尚未找到数据中心买家,总成本也未公布。
SB Energy is advancing the 500 MW Lyra Battery Energy Storage System in Borden County, Texas, backed by PUCT Docket No. 59183 transmission approvals connecting to ERCOT.
The New York State Board on Electric Generation Siting and the Environment approved the Article 10 Certificate; commercial operation is scheduled for late 2026.[1]
NextEra Energy Resources is investing 345M USD in the Excelsior Energy Center in the Town of Byron, Genesee County, New York, deploying 280 MW of solar power and a 20 MW battery under a New York Article 10 permit.
The Public Service Commission of Wisconsin approved project construction and the multi-utility purchase agreement; commercial operation is scheduled for late 2026.[1]
Invenergy developed and utilities We Energies, WPS, and MGE purchased the 649M USD Koshkonong Solar Energy Center in southeast Dane County, Wisconsin, featuring 300 MW of solar and a 165 MW / 660 MWh battery.
Edwards Sanborn solar and storage complex, near Mojave and Rosamond, Kern County, California, United States (OpenStreetMap centroid of the complex; EdSan 2 parcel not published)Terra-Gen
DTE Energy[1] broke ground following MPSC approval and plant demolition; utility filings and public reports schedule commercial operation for late 2026.
DTE Energy is investing 460M USD to redevelop its retired 1924 Trenton Channel coal plant along the Detroit River in Wayne County, Michigan, into a 220 MW / 880 MWh lithium-ion battery storage system, backed by 140M USD in IRA tax incentives.
Power Magazine和Solar Power World:“预计2027年投运”;Korea Times[5]:商业运营计划于2027年开始。均未说明月份;ERCOT队列条目26INR0330列出的拟定商业运营日期为2027年9月,EIA-860M列为2027年7月1日。BIC Magazine早先的报道称为2026年底。
About 11000 N McCornick Road, Millard County, near Delta, Utah, United States (address from the county agenda; coordinates approximate to Delta)Joule Capital Partners
Carlyle旗下投资组合公司Copia Power正在亚利桑那州马里科帕县的Harquahala园区为Arizona Public Service建设550 MW的Maricopa Energy Center太阳能项目及2,200 MWh储能,融资包括17.1亿美元债务融资和8.9亿美元税务股权承诺;项目总成本未公布。