已延期日期确定性: 已延期日期已变动来源对日期的表述有多确定:已确认、已排期、预估、已推迟或未核实。显示所有“已延期”的图钉延期5个月可信度 68%总体可信度: 68%该图钉的来源和参考资料对其日期的支持程度。包括来源在内的 5 份资料对图钉开始和结束时间支持程度的加权平均;资料每比最新的一份旧 180 天,权重减半显示所有可信度为 50%–74% 的图钉The water superintendent says "We'll be delivering water spring of 2027 from the treatment plant" and the headline gives May 2027; the plan was fall 2026.[1]
Billings' $75 million West End plant, the biggest public works project in city history, is now due to deliver water in May 2027 after electrical supply chain problems pushed it from fall 2026. Reservoir storage is targeted for fall 2027.