ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
Houston First[1][2] says the fully financed first phase is "on schedule to open in May 2028", a month rather than a day.
A 700,000-square-foot building joined to the George R. Brown Convention Center, holding two exhibition halls, an atrium hall and the largest ballroom in Texas, plus a 100,000-square-foot pedestrian plaza linking it to the Toyota Center. Houston First financed this first phase of its $2 billion convention district transformation with about $1.38 billion of hotel occupancy tax and special revenue bonds.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 7 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
EIA’s[2] September 2026 preliminary inventory records a forecast operation month 2028-05. The first day of May 2028 is an estimated month-only display marker, not an exact opening day. The forecast does not prove physical completion and can change in later monthly inventories.
EIA’s September 2026 preliminary inventory identifies AEUG Fleming Solar, LLC, plant 64658, in Fleming County, KY, with 188.5 MW electrical generation nameplate. The listed stage is (U) Under construction, less than or equal to 50 percent complete. Operation is forecast for 2028-05; this is a preliminary survey estimate, not an achieved opening or capacity commitment.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins3 years late65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 5 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
EIA’s[2] September 2026 preliminary inventory records a forecast operation month 2028-05. The first day of May 2028 is an estimated month-only display marker, not an exact opening day. The forecast does not prove physical completion and can change in later monthly inventories.
EIA’s September 2026 preliminary inventory identifies Accalia Point Solar, LLC, plant 66673, in Cameron County, TX, with 190.5 MW electrical generation nameplate. The listed stage is (P) Planned for installation, but regulatory approvals not initiated. Operation is forecast for 2028-05; this is a preliminary survey estimate, not an achieved opening or capacity commitment.
Oso Negro Clean Energy Storage Facility, West Mesa Industrial & Paseo del Volcan Corridor, Albuquerque, Bernalillo County, NM 87121Oso Negro Energy Storage LLC
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
PNM[1] transmission interconnection queue and NMPRC resource adequacy filings schedule the 100 MW Oso Negro battery energy storage project for May 2028 commercial operation.
Development of the Oso Negro Clean Energy Storage Facility in Bernalillo County, New Mexico. Delivering 100 MW / 400 MWh of standalone four-hour lithium-ion battery energy storage along the Public Service Company of New Mexico (PNM) West Mesa 115 kV / 345 kV transmission corridor, the project strengthens grid reliability for the Albuquerque metropolitan load pocket.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
PJM[1] generation interconnection queue filings and Service Agreement No. 7668 specify a May 2028 target commercial operation date.
Savion is developing the 100 MW standalone Threeforks Energy Storage facility near Inez in Martin County, Kentucky. Tracked in the PJM Interconnection queue under position AF1-162 and governed by PJM Service Agreement No. 7668, the utility-scale battery energy storage system interconnects at the Inez 138 kV substation on the American Electric Power transmission system to support Central Appalachian grid reliability.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins58% CONFIDENCEOverall confidence: 58%How well the pin's source and references back up its dates.Weighted average of how firmly 2 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
Date is the MISO queue proposed COD of 2028-05-31 per Infrasure[1]; no developer announcement.
MISO queue entry J3402 is a proposed 200 MW battery project in Juneau County, Wisconsin, interconnecting at the New J1502 TO Switching Station (Emerson) in the ATC system. It entered the queue in April 2024 with a proposed COD of May 31, 2028.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
NextEra's project page gives a May 2028 earliest operations date subject to approvals; no permit or construction date is published.[1]
NextEra Energy Resources proposes Sailors Solar, a photovoltaic project of up to 160 MW on about 1,300 acres of city-owned Monolith Ranch southwest of Laramie. NextEra says operations could begin as early as May 2028, subject to local and state approvals.
Cass County, Missouri, Pleasant Hill POI context; exact battery parcel pending
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 1 reference supports the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
May 17, 2028 is SPP’s[1] proposed COD; study status and Yes deviation flag make delivery unconfirmed.
SPP lists GEN-2024-170 as 280 MW battery storage in Cass County, Missouri, at Pleasant Hill 345 kV. Proposed COD is May 17, 2028; the request remains in DISIS study with a deviating timeline flag.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins50% CONFIDENCEOverall confidence: 50%How well the pin's source and references back up its dates.Weighted average of how firmly 1 reference, the source included, supports the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
ClinicalTrials.gov[1] lists 2028-05-22 as the estimated primary completion date; a sponsor's estimate, and trials of this size routinely slip.
Boehringer Ingelheim's phase 3 trial of Vicadrostat in heart failure reaches primary completion, the point at which the last participant's primary outcome is measured. The trial enrolled 6,000 participants. This study is open to adults aged 18 or above legal age with heart failure. People can join the study if they have heart failure symptoms and a left ventricular ejection fraction (LVEF) of 40% or more. The purpose of this study is to find out whether vicadrostat (BI 690517) in combination with empagliflozin helps people with heart failure. Participants are put into 2 groups by chance. Every participant has an equal chance of being in each group. The groups are: * Vicadrostat/empagliflozin group: participants take vicadrostat/empagliflozin as tablets once a day. * Placebo/empagliflozin group: participants take placebo/empagliflozin as tablets once a day. Participants can stay in the study as long as they benefit from treatment and can tolerate it. During this time, they visit their doctors regularly. The doctors regularly check participants' health and take note of any unwanted effects.
35 Electric Avenue, Brighton, Boston, Massachusetts; address-context point, not surveyed battery footprintFlatiron Energy
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
ISO proposed in-service date, also current queue target; future requested date, not confirmed operation.[1]
ISO New England’s January 6, 2025 reliability letter identifies Flatiron’s Lite Brite Storage request in Boston at 300 MW discharge, 150 MW charging and 1,200 MWh, targeting May 26, 2028. The local 200 MW planning proposal has a different stated scope.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 4 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
LAWA's[1][2][3][4] project page: "Ingress Roadways completion is anticipated in May 2028. Project completion is anticipated mid-2030"; a month takes its last day.
The inbound half of LAX's 4.4-mile roadway rebuild, which separates airport traffic from Sepulveda Boulevard and neighbourhood streets, is due in May 2028, two months before the Games.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 7 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
Pennrose's[1] May 2028 completion is conditional on funding that had not been awarded in any source found, and a lawsuit seeks to block the land sale; the date is a developer target only.
Planned 60-home senior community on the 1016–1024 North 2nd Street site, with studios and one-bedrooms for adults 55+ earning no more than 60% AMI. Completion targeted for May 2028, contingent on funding.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 7 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
Pin date 2028-05-31 reflects McShane's May 2028 target; Atlanta Housing[4] says only spring 2028. Both are targets, not an opening.
The Overlook at Garson will add 130 affordable apartments near Lindbergh MARTA and the future Northeast Beltline. McShane expects completion in May 2028; income eligibility ranges from 50% to 80% AMI.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins50% CONFIDENCEOverall confidence: 50%How well the pin's source and references back up its dates.Weighted average of how firmly 1 reference, the source included, supports the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
Estimated construction completion: approximate calendar placement from the published year, month, or season; the selected day is a placeholder, not a verified event day. This is not an opening date.[1]
Microsoft describes Ginger East as being built by Weitz Construction, with construction completion forecast for mid-2028. Completion does not establish operational availability; the exact parcel is unverified.
County Road MM, northeast of Hereford, Deaf Smith County, Texas, 79045, United StatesGoogle
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 5 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
Target commercial operation beginning in 2028 aligned with ERCOT and EIA-860M interconnection queue filings for IP Roman generation and Deaf Smith County Chapter 312 tax abatement milestones.[1]
Google and Intersect Power affiliate IP Roman III Gas are developing Project Roman, a hyperscale data center campus powered by the 1,474 MW gas-fired Roman Energy Center across 3,700 acres in Deaf Smith County, Texas; total capital cost has not been published while county tax abatements anticipate over 108 million USD in PILOT revenue.
1657 Alviso-Milpitas Road, San Jose, CA 95002Microsoft
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 2 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
June 1, 2028 remains an unverified legacy tracker estimate, not an operator-published COD. Microsoft[2] confirms physical work, but its summer-2026 site-preparation target is not full data-center opening.
The California Energy Commission identifies Microsoft’s two-building San Jose project at 1657 Alviso-Milpitas Road, with a maximum electrical load of 99 MW and estimated load of 77 MW. A verified total project budget and COD remain unavailable.
Estimated: QTS Denver Data Center Campus, East 56th Avenue, Aurora, Adams County, CO 80011QTS Data Centers
UNVERIFIEDDate confidence: UNVERIFIEDNo wording about the date was foundHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all UNVERIFIED pins40% CONFIDENCEOverall confidence: 40%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins at 49% confidence or below
Separate construction cost, IT power, floor area and an opening date for this building or phase have not been verified. Published campus figures do not establish independent component figures.
Wilson County, Texas, United States (south of San Antonio)Advanced Power
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 7 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
EIA’s[2] September 2026 preliminary inventory records a forecast operation month 2028-06. The first day of June 2028 is an estimated month-only display marker, not an exact opening day. The forecast does not prove physical completion and can change in later monthly inventories.
EIA’s September 2026 preliminary inventory identifies Alina Energy LLC, plant 67250, in Wilson County, TX, with 200 MW electrical generation nameplate. The listed stage is (P) Planned for installation, but regulatory approvals not initiated. Operation is forecast for 2028-06; this is a preliminary survey estimate, not an achieved opening or capacity commitment.
Jackson County Hyperscale Campus, Widows Creek Site, Bridgeport, AL 35740
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 2 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
Estimated commercial operation target of June 2028 based on planned campus phase schedule and utility power delivery filings.[1]
Google LLC expansion of the Jackson County Hyperscale Computing Campus situated at the former Widows Creek coal plant site in Bridgeport, Jackson County, Alabama. Building 3 encompasses approximately 350,000 square feet delivering 150 MW of dedicated critical IT compute capacity powered through dedicated clean energy PPAs with Tennessee Valley Authority (TVA).
Estimated: 22151 NW Service Road, Warrenton, Warren County, Missouri 63383, United States (approximate: Warrenton city centroid used; the street address comes from the city's filing)Crusoe
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 6 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
Cleanview state-leads planned COD: 2028 (Crusoe Warrenton Building 1).[1]
Crusoe's affiliate Warrenton DC Owner 1 LLC plans two 805,000 sq ft data centers on about 337 acres in Warrenton, Missouri (600 MW across two 300 MW buildings per Cleanview; no MW figure from Crusoe or Ameren), with about 8.37B USD of servers per phase in the city's filing and Meta reportedly contracted for capacity.
DELAYEDDate confidence: DELAYEDThe date has movedHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all DELAYED pins17 months late55% CONFIDENCEOverall confidence: 55%How well the pin's source and references back up its dates.Weighted average of how firmly 5 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
AI Weekly[3] (19 Jul 2026): "targeting first operations by summer 2028"; DCD (12 Jan 2026): IID said "the project could go live as early as January 2027". Both predate the 9 Sep 2026 ruling, so the real date is unknown.
Imperial Valley Computer Manufacturing's 330 MW, roughly 10B USD, 950,000 sq ft campus near the City of Imperial lost its county approval on 9 September 2026 when an Imperial County judge ruled CEQA review was required; the developer plans to seek a new trial and appeal.
Route 6 and Gun Club Road, Morris, Grundy County, Illinois, United StatesTract
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 5 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
Bisnow[5] (27 Jan 2026): "Initial energization is targeted for June 2028"; Tract's FAQ hosted by the City of Morris: "Initial power delivery to the site is expected in Q2 of 2028". Full 1 GW load ramp by 2032 per Bisnow.
Tract bought a 343-acre zoned site in Morris, Grundy County, Illinois in January 2026 for a campus of up to 1,000 MW (1GW) with ComEd power, initial energization targeted for June 2028; the land cost about 51.5M USD and no project cost has been published.
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
Unverified legacy June 2028 COD; county completeness determination is not an approved schedule.[1]
Shawnee County marked Compass’s CU-26-203 application complete September 9,2026, without approving its merits or scheduling a hearing. The applicant’s revised plan gives 400 MW final IT load across ten buildings and roughly 500–600 MW total demand, replacing the 153 MW tracker claim.
12899 Moores Chapel Road, Charlotte, Mecklenburg County, NC 28214Digital Realty
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 3 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
Unverified legacy June 2028 estimate; opened issuer/planning records establish scope, not a commissioning date.[1]
Digital Realty’s earnings release establishes up to 400 MW IT capacity for its Charlotte land acquisition. City planning records describe 156.23 acres and up to 3 million square feet; the $160M land purchase is not a total campus budget.
North Stadium Drive & Parvin Road, Kansas City, Clay County, MO 64161Google LLC
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 2 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
Unverified legacy June 2028 COD; current operator listing gives no exact commissioning date.[1]
The March 20,2024 announcement establishes a$1 B Kansas City data-center investment. Google’s current location page describes two developing facilities and 400 MW of new grid clean-energy capacity, which is not a published 217 MW campus IT load.