Energy: withdrawn interconnection request · تم التحقق 2026-10-30
تُبرز المرحلة المعلنة فقط. تميز الأرقام والتواريخ بين المخطط والمثبت.
600.0 MW former requested power; not current generation or battery operation.
“"summerNetMW":600.0”
2026-10-30: withdrawal recorded in the opened queue. The actual withdrawal day is not published.
“"applicationStatus":"Withdrawn"”
Withdrawn request; this does not establish site-wide project cancellation.
“"applicationStatus":"Withdrawn"”
Solar; point of interconnection Smalling.
“"fuelType":"Solar"”
Withdrawal recorded in MISO queue (date checked; withdrawal day unpublished)
“"applicationStatus":"Withdrawn"”
يتابع هذا الدبوس الأخبار: فهو يعرض ما هو معروف الآن، وهنا ما تغيّر وما الذي أدى إليه.
تم التعديلبواسطة @ThePinGang
… no four-hour duration or battery MWh is inferred. The MISO queue was checked on October 30, 2026 and records this request as withdrawn. The actual withdrawal date is not published; the timeline milestone records the date checked.
تم التعديلبواسطة @ThePinGang
Smalling Solar Energy LLC has completed MISO Definitive Planning Studies and local zoning review for the 620M USD, 600 MWac Smalling Clean Solar Farm in Richland Parish, Louisiana.J2519 is a 600 MW photovoltaic generation interconnection request in Richland, LA. The grid operator lists its queue status as Withdrawn. The requested in-service date is 2026-10-31; this is a planning date.
Smalling Solar Energy finalized MISO DPP generatorJ2519 is a 600 MW photovoltaic generation interconnection queue studies. Supplies 600 MWac of single-axis tracking bifacial solar photovoltaic capacity across 4,200 acres. Represents an estimated 620 million USD clean energy capital development in northeastern Louisiana. Directly interconnects to Entergy Louisiana's 230/500 kV Rayville to Franklin transmission line. Generates approximately 1,180,000 MWh annually, delivering economic development and carbon-free energy torequest in Richland, LA. The grid operator lists its queue status as Withdrawn. The requested in-service date is 2026-10-31; this is a planning date. The point of interconnection is Smalling. Queue processing status does not establish physical construction or commercial operation. No exact-scope construction budget is published in the Delta region. Timeline: planned project targeting commercial operation in April 2029 (estimated) under MISO interconnection queue and state regulatory schedules.cited grid record. Battery power is distinct from stored energy; no four-hour duration or battery MWh is inferred.
تم التعديلبواسطة @ThePinGang
… development and carbon-free energy to the Delta region. Timeline: planned project targeting commercial operation in April 2029 (estimated) under MISO interconnection queue and state regulatory schedules.
صور من القرّاء، منفصلة عن وسائط الدبوس الموثّقة بمصادر. قيّم ما أكلته أو رأيته، وفي دبوس المطعم وسّم الأطباق مباشرة على صورتك.
المدخل الأول هو دائمًا مصدر الدبوس. الثقة الإجمالية متوسط مرجّح لمدى قوة دعم كل مرجع لوقتَي البدء والانتهاء المستخدمين أعلاه؛ ويقل وزن المرجع إلى النصف عن كل 180 يومًا يسبق بها أحدث مرجع.
هل ينقص شيء أو يوجد خطأ؟ قله بكلماتك: رابط يدعم هذا الدبوس، أو تاريخ بدء أو انتهاء مختلف مع السبب، أو معلومة ينقصها أو يخطئ فيها. يفحص الذكاء الاصطناعي ذلك بمقارنته بمصادر هذا الدبوس، ويبحث عن مصادر أفضل، ويضيف أي صفحة تدعم كلامك. وتبقى مصادر الدبوس نفسه الأثقل وزنًا. كما تُفحص الصورة التي تُظهر شيئًا آخر أو تُظهره بشكل سيئ، فتُنزَّل أو تُستبدل.
العنوان الأصلي: Smalling: 600 MW Solar Interconnection Request J2519 — Withdrawn
تم فحص قائمة انتظار MISO في 30 أكتوبر 2026 وتم تسجيل هذا الطلب على أنه مسحوب. لم يتم نشر تاريخ الانسحاب الفعلي؛ يسجل الحدث الرئيسي للخط الزمني التاريخ المحدد.[1]
Power generation600 MW · J2519: 600 MW requested photovoltaic generation. Queue status: Withdrawn. Requested date: 2026-10-31. Not current measured generation; withdrawn request. No annual energy or battery MWh inferred. · source