Port Waratah Begins Shiploader 7.09 Overhaul at Kooragang Terminal
- Port Waratah Coal Services committed to a roughly $270 million programme (announced 6 May 2025) so Kooragang Terminal meets demand beyond 2030[2]
- A four-month outage of Shiploader 7.09 for life-extension works begins in July 2025, with further outages over four years including 7.10[2]
- A new shiploader at the K4 berth replaces Shiploader 7.08 (operating since 1984), expected in operation in 2028[2]
- Contracts for the new shiploader and the 7.09 works are with Civmec Construction and Engineering[2]
References 290% CONFIDENCE
The first entry is always the pin's source. Overall confidence is a weighted average of how firmly each reference supports the start and end times used above; a reference counts half as much for every 180 days older than the newest.
- [1]90%youtube.com/watch?v=3yForRqB2fAyoutube.com· Posted Sep 15, 2026· Starts Jul 1, 2025 ✓· 87% of score
Port Waratah's 6 May 2025 news release states the four-month refurbishment outage on Shiploader 7.09 began in July 2025.
- [2]90%Fit for the long term: Port Waratah invests $270 million in shiploaderspwcs.com.au· Published May 6, 2025· 13% of score
Port Waratah's own news release announcing the $270 million shiploader program and the July 2025 Shiploader 7.09 outage.[1]
Suggest a correction
Something missing or wrong? Say it in your own words: a link that backs this pin up, a different start or end date and why, or a fact it lacks or gets wrong. The AI checks it against this pin's sources, searches for better ones, and adds any page that backs you up. The pin's own sources still count most.