China’s official July 19, 2025 government/Xinhua report confirms construction launch and publishes approximately CNY1.2 trillion total investment for a five-cascade hydropower programme. This full-complex investment is not a budget for one individual dam. GEM’s inspected August 2026 inventory reports 60,000 MW for the construction project; it is a design rating, not existing operating output. The government groundbreaking article itself does not publish the MW figure.
China’s official July 19, 2025 government/Xinhua report confirms construction launch and publishes approximately CNY1.2 trillion total investment for a five-cascade hydropower programme. This full-complex investment is not a budget for one individual dam. GEM’s inspected August 2026 inventory reports 60,000 MW for the construction project; it is a design rating, not existing operating output. The government groundbreaking article itself does not publish the MW figure.
Published project rating: 60000 MW. 60,000 MW design capacity from GEM August 2026 inventory, not independently given in the cost announcement
Retained only with documented physical construction, commissioning or 2025–2026 opening and published project-specific costs and electrical output. Costs use the published scope and currency; no benchmark estimates or currency conversions. MW is power capacity, not annual electricity production. Expected annual energy, where given, is a forecast. The map point is a reported plant/project location and may be approximate. Matching inventory views and excluded expansion proposals are not additive capacity.
Groundbreaking event for the lower Yarlung Zangbo hydropower complex, July 19, 2025; not a completed dam. Credit: Project operator; individual photographer not named on source page. Source and gallery; original media.
Meeting associated with the lower Yarlung Zangbo project groundbreaking visit, July 19, 2025; not a dam construction photograph. Credit: Project operator; individual photographer not named on source page. Source and gallery; original media.
編集@ThePinGang による
変更前
China’s official July 19, 2025 government/Xinhua report confirms construction launch and publishes approximately CNY1.2 trillion total investment for a five-cascade hydropower programme. This full-complex investment is not a budget for one individual dam. GEM’s inspected August 2026 inventory reports 60,000 MW for the construction project; it is a design rating, not existing operating output. The government groundbreaking article itself does not publish the MW figure.
China’s official July 19, 2025 government/Xinhua report confirms construction launch and publishes approximately CNY1.2 trillion total investment for a five-cascade hydropower programme. This full-complex investment is not a budget for one individual dam. GEM’s inspected August 2026 inventory reports 60,000 MW for the construction project; it is a design rating, not existing operating output. The government groundbreaking article itself does not publish the MW figure.
Published project rating: 60000 MW. 60,000 MW design capacity from GEM August 2026 inventory, not independently given in the cost announcement
Retained only with documented physical construction, commissioning or 2025–2026 opening and published project-specific costs and electrical output. Costs use the published scope and currency; no benchmark estimates or currency conversions. MW is power capacity, not annual electricity production. Expected annual energy, where given, is a forecast. The map point is a reported plant/project location and may be approximate. Matching inventory views and excluded expansion proposals are not additive capacity.
編集@ThePinGang による
読者の写真で、出典付きのピンのメディアとは別に表示されます。食べたものや見たものを評価でき、レストランのピンでは写真上に料理をタグ付けできます。
最初の項目は常にピンの出典です。全体の確度は、各資料が上記の開始・終了時刻をどれだけ強く裏付けているかの加重平均です。最新の資料より180日古くなるごとに、重みは半分になります。
文書で確認された物理的なマイルストーン、または日付付きの進捗・報告の目安。期間末の日付は報告された月・四半期のみを表し、正確な稼働日を作り出すものではない。情報源の推定値はそのように表示され、確定した将来の開業日としては扱わない。
China’s official July 19, 2025 government/Xinhua report confirms construction launch and publishes approximately CNY1.2 trillion total investment for a five-cascade hydropower programme. This full-complex investment is not a budget for one individual dam. GEM’s inspected August 2026 inventory reports 60,000 MW for the construction project; it is a design rating, not existing operating output. The government groundbreaking article itself does not publish the MW figure.[1]
Published project rating: 60000 MW. 60,000 MW design capacity from GEM August 2026 inventory, not independently given in the cost announcement[1]
足りない点や誤りがありますか? このピンを裏付けるリンク、別の開始日・終了日とその理由、欠けている情報や誤っている情報を、自由に書いてください。AIがこのピンの出典と照らし合わせ、より良い情報源を探し、裏付けとなるページがあれば参考資料として追加します。ピン自身の出典が引き続き最も重視されます。AIは画像も確認します。別のものが写っている画像や写りの悪い画像は、後ろに回すか差し替えます。
元のタイトル: Lower Yarlung Zangbo five-station hydropower complex — under construction
2025年7月19日の中国政府・新華社の公式報道は、着工を確認し、5段階のカスケード水力発電プログラム全体の総投資額を約1.2兆人民元と公表している。この複合施設全体の投資額は、個々のダム1基の予算ではない。GEMが確認した2026年8月の一覧では、建設中のプロジェクトは6万MWとされているが、これは設計定格であり、既存の稼働出力ではない。政府の起工式の記事自体にはMWの数値は載っていない。[1][2]
2025年7月19日の中国政府・新華社の公式報道は、着工を確認し、5段階のカスケード水力発電プログラム全体の総投資額を約1.2兆人民元と公表している。この複合施設全体の投資額は、個々のダム1基の予算ではない。GEMが確認した2026年8月の一覧では、建設中のプロジェクトは6万MWとされているが、これは設計定格であり、既存の稼働出力ではない。政府の起工式の記事自体にはMWの数値は載っていない。[2]
公表されたプロジェクト定格:6万MW。GEMの2026年8月の一覧による設計容量6万MWで、費用発表では独自に示されていない[1]
掲載対象は、物理的な建設、試運転、または2025~2026年の開業が確認でき、プロジェクト固有の費用と電気出力が公表されているものに限ります。費用は公表された範囲と通貨を使用し、基準推計や通貨換算は行いません。MWは出力容量であり、年間発電量ではありません。年間発電量の見込みが示されている場合は予測値です。地図上の点は報告された発電所・プロジェクトの所在地であり、おおよその位置の場合があります。該当するインベントリ表示や除外された拡張提案は加算できる容量ではありません。
2025年7月19日のヤルンツァンポ川下流水力発電複合施設の起工式。完成したダムではない。 クレジット:新華社、中華人民共和国国務院経由。 出典とギャラリー、 元のメディア。
北京での中国雅江集団の発足式。2025年7月19日付の政府によるヤルンツァンポ川下流プロジェクトの報道に掲載された。これは企業の発足式であり、ダム建設地での起工式や工事の進捗ではない。 クレジット:新華社、中華人民共和国国務院経由。 出典とギャラリー、 元のメディア。