Energy: battery storage · 確認日 2026-10-30
確認された段階のみ強調しています。数値と日付は計画と実証済みを区別しています。
500 MW battery storage request; preliminary interconnection scope, not measured output.
“"poiName":"Stein - Rapson 345 kV line","summerNetMW":500.0”
2025-04-01; requested date only, not an achieved opening.
“"projectNumber":"J2590","queueDate":"2022-09-15T04:00:00+00:00","inService":"2025-04-01T04:00:00+00:00"”
Active; queue status does not establish physical construction or commercial service.
“"applicationStatus":"Active","sisPhase1":"","postGIAStatus":"Not Started"”
Battery Storage; Stein - Rapson 345 kV line.
“"fuelType":"Battery Storage","facilityType":"Battery Storage"”
Interconnection request received
“"projectNumber":"J2590","queueDate":"2022-09-15T04:00:00+00:00"”
Requested in-service date
“"projectNumber":"J2590","queueDate":"2022-09-15T04:00:00+00:00","inService":"2025-04-01T04:00:00+00:00"”
このピンはニュースを追い、最新の情報を表示しています。何が変わり、何がきっかけだったかをここに示します。
編集@ThePinGang による
ITC Michigan and MISO have advanced system stability and generator interconnection engineering for the 500M USD, 500 MW / 2,000 MWh Stein-Rapson Clean Energy Storage Center in Huron County, Michigan.J2590 is a 500 MW battery storage interconnection request in Huron, MI. The grid operator lists its queue status as Active. The requested in-service date is 2025-04-01; this is a planning date.
ITC Michigan progressed MISO DPP Definitive Planning Study Queue J2140 engineering for the facility. Features 500 MW / 2,000 MWh of utility-grade containerized lithium iron phosphate battery storage. Represents an estimated 500 million USD private clean energy development in Michigan's Thumb region. Interconnects to ITC Michigan's 345 kV Stein to Rapson transmission line. Captures high-volume Thumb wind and solar generation, resolving regional transmission bottlenecks. Timeline: planned project targeting commercial operation in August 2029 (estimated) under MISO interconnection queue and state regulatory schedules.J2590 is a 500 MW battery storage interconnection request in Huron, MI. The grid operator lists its queue status as Active. The requested in-service date is 2025-04-01; this is a planning date. The point of interconnection is Stein - Rapson 345 kV line. Queue processing status does not establish physical construction or commercial operation. No exact-scope construction budget is published in the cited grid record. Battery power is distinct from stored energy; no four-hour duration or battery MWh is inferred.
編集@ThePinGang による
… wind and solar generation, resolving regional transmission bottlenecks. Timeline: planned project targeting commercial operation in August 2029 (estimated) under MISO interconnection queue and state regulatory schedules.
読者の写真で、出典付きのピンのメディアとは別に表示されます。食べたものや見たものを評価でき、レストランのピンでは写真上に料理をタグ付けできます。
最初の項目は常にピンの出典です。全体の確度は、各資料が上記の開始・終了時刻をどれだけ強く裏付けているかの加重平均です。最新の資料より180日古くなるごとに、重みは半分になります。
2025-04-01 は、相互接続記録の要求されたサービス開始日であり、検証された開通日または商業運用日ではありません。
足りない点や誤りがありますか? このピンを裏付けるリンク、別の開始日・終了日とその理由、欠けている情報や誤っている情報を、自由に書いてください。AIがこのピンの出典と照らし合わせ、より良い情報源を探し、裏付けとなるページがあれば参考資料として追加します。ピン自身の出典が引き続き最も重視されます。AIは画像も確認します。別のものが写っている画像や写りの悪い画像は、後ろに回すか差し替えます。
元のタイトル: Stein-Rapson: 500 MW Battery Interconnection Request J2590
Power storage500 MW · J2590: 500 MW requested battery storage. Queue status: Active. Requested date: 2025-04-01. Not current measured generation; No annual energy or battery MWh inferred. · source