Energy: battery storage · 確認日 2026-10-30
確認された段階のみ強調しています。数値と日付は計画と実証済みを区別しています。
205 MW battery storage request; preliminary interconnection scope, not measured output.
“"poiName":"Hazleton","summerNetMW":205.0”
2028-06-30; requested date only, not an achieved opening.
“"projectNumber":"J3780","queueDate":"2024-04-18T04:00:00+00:00","inService":"2028-06-30T04:00:00+00:00"”
Active; queue status does not establish physical construction or commercial service.
“"applicationStatus":"Active","sisPhase1":"","postGIAStatus":""”
Battery Storage; Hazleton.
“"fuelType":"Battery Storage","facilityType":"Battery Storage"”
Interconnection request received
“"projectNumber":"J3780","queueDate":"2024-04-18T04:00:00+00:00"”
Requested in-service date
“"projectNumber":"J3780","queueDate":"2024-04-18T04:00:00+00:00","inService":"2028-06-30T04:00:00+00:00"”
このピンはニュースを追い、最新の情報を表示しています。何が変わり、何がきっかけだったかをここに示します。
編集@ThePinGang による
Alliant Energy / Interstate Power and Light development of the Hazleton Clean Energy Storage Center in Buchanan County, Iowa. TheJ3780 is a 205 MW / 820 MWh battery facility connects to the 345 kV Hazleton substation hub, providing essential grid flexibility, wind generation firming, and local transmission support across northeastern Iowa.battery storage interconnection request in Buchanan, IA. The grid operator lists its queue status as Active. The requested in-service date is 2028-06-30; this is a planning date.
Alliant Energy / Interstate Power and Light advanced engineering reviews for the Hazleton Clean Energy Storage Center. Features 205 MW / 820 MWh of grid-scale battery storage capacity in Buchanan County, Iowa. RepresentsJ3780 is a 205 MW battery storage interconnection request in Buchanan, IA. The grid operator lists its queue status as Active. The requested in-service date is 2028-06-30; this is a 220 million USD private clean energy infrastructure investment in eastern Iowa. Connects to the 345 kV Hazleton substation hub within the MISO transmission footprint. Enhances grid flexibility, firms regional wind generation, and reinforces transmission reliability. Timeline: planned project targeting commercial operation in June 2028 (estimated) under MISO interconnection queue and state regulatory schedules.planning date. The point of interconnection is Hazleton. Queue processing status does not establish physical construction or commercial operation. No exact-scope construction budget is published in the cited grid record. Battery power is distinct from stored energy; no four-hour duration or battery MWh is inferred.
編集@ThePinGang による
… firms regional wind generation, and reinforces transmission reliability. Timeline: planned project targeting commercial operation in June 2028 (estimated) under MISO interconnection queue and state regulatory schedules.
編集@ThePinGang による
読者の写真で、出典付きのピンのメディアとは別に表示されます。食べたものや見たものを評価でき、レストランのピンでは写真上に料理をタグ付けできます。
最初の項目は常にピンの出典です。全体の確度は、各資料が上記の開始・終了時刻をどれだけ強く裏付けているかの加重平均です。最新の資料より180日古くなるごとに、重みは半分になります。
足りない点や誤りがありますか? このピンを裏付けるリンク、別の開始日・終了日とその理由、欠けている情報や誤っている情報を、自由に書いてください。AIがこのピンの出典と照らし合わせ、より良い情報源を探し、裏付けとなるページがあれば参考資料として追加します。ピン自身の出典が引き続き最も重視されます。AIは画像も確認します。別のものが写っている画像や写りの悪い画像は、後ろに回すか差し替えます。
元のタイトル: Hazleton: 205 MW Battery Interconnection Request J3780
Power storage205 MW · J3780: 205 MW requested battery storage. Queue status: Active. Requested date: 2028-06-30. Not current measured generation; No annual energy or battery MWh inferred. · source