Energy: battery storage · 確認日 2026-10-30
確認された段階のみ強調しています。数値と日付は計画と実証済みを区別しています。
250 MW battery storage request; preliminary interconnection scope, not measured output.
“"poiName":"Batesville 138kV Substation","summerNetMW":250.0”
2027-09-30; requested date only, not an achieved opening.
“"projectNumber":"J2581","queueDate":"2022-09-15T04:00:00+00:00","inService":"2027-09-30T04:00:00+00:00"”
Active; queue status does not establish physical construction or commercial service.
“"applicationStatus":"Active","sisPhase1":"","postGIAStatus":"Not Started"”
Battery Storage; Batesville 138kV Substation.
“"fuelType":"Battery Storage","facilityType":"Battery Storage"”
Interconnection request received
“"projectNumber":"J2581","queueDate":"2022-09-15T04:00:00+00:00"”
Requested in-service date
“"projectNumber":"J2581","queueDate":"2022-09-15T04:00:00+00:00","inService":"2027-09-30T04:00:00+00:00"”
このピンはニュースを追い、最新の情報を表示しています。何が変わり、何がきっかけだったかをここに示します。
編集@ThePinGang による
MISO regional transmission interconnection development of the Batesville Energy Storage Center in Ripley County, Indiana. SupplyingJ2581 is a 250 MW / 1,000 MWh of utility-scale battery energy storage, the facility interfaces with the Batesville 138 kV substation to provide rapid frequency response, grid inertia, and capacity firming across southeastern Indiana.battery storage interconnection request in Ripley, IN. The grid operator lists its queue status as Active. The requested in-service date is 2027-09-30; this is a planning date.
Batesville Energy Storage LLC submitted interconnection filings for the Batesville Energy Storage CenterJ2581 is a 250 MW battery storage interconnection request in Ripley County, Indiana. Deploys 250 MW / 1,000 MWh of utility-scale four-hour duration lithium-ion battery storage. Represents an estimated 250 million USD private clean energy infrastructure investment in southeastern Indiana. Interconnects to the Batesville 138 kV substation within the MISO transmission footprint. Provides essential rapid frequency regulation, system inertia, and regional capacity firming. Timeline: planned project targeting commercial operation in September 2027 (estimated) under MISO interconnection queue and state regulatory schedules.Ripley, IN. The grid operator lists its queue status as Active. The requested in-service date is 2027-09-30; this is a planning date. The point of interconnection is Batesville 138kV Substation. Queue processing status does not establish physical construction or commercial operation. No exact-scope construction budget is published in the cited grid record. Battery power is distinct from stored energy; no four-hour duration or battery MWh is inferred.
編集@ThePinGang による
… frequency regulation, system inertia, and regional capacity firming. Timeline: planned project targeting commercial operation in September 2027 (estimated) under MISO interconnection queue and state regulatory schedules.
編集@ThePinGang による
読者の写真で、出典付きのピンのメディアとは別に表示されます。食べたものや見たものを評価でき、レストランのピンでは写真上に料理をタグ付けできます。
最初の項目は常にピンの出典です。全体の確度は、各資料が上記の開始・終了時刻をどれだけ強く裏付けているかの加重平均です。最新の資料より180日古くなるごとに、重みは半分になります。
足りない点や誤りがありますか? このピンを裏付けるリンク、別の開始日・終了日とその理由、欠けている情報や誤っている情報を、自由に書いてください。AIがこのピンの出典と照らし合わせ、より良い情報源を探し、裏付けとなるページがあれば参考資料として追加します。ピン自身の出典が引き続き最も重視されます。AIは画像も確認します。別のものが写っている画像や写りの悪い画像は、後ろに回すか差し替えます。
元のタイトル: Batesville: 250 MW Battery Interconnection Request J2581
Power storage250 MW · J2581: 250 MW requested battery storage. Queue status: Active. Requested date: 2027-09-30. Not current measured generation; No annual energy or battery MWh inferred. · source