発表済み
Energy: photovoltaic generation · 確認日 2026-10-30
確認された段階のみ強調しています。数値と日付は計画と実証済みを区別しています。
250 MW photovoltaic generation request; preliminary interconnection scope, not measured output.
“"poiName":"Cedar Mountain - Lyon County 345.0kV","summerNetMW":250.0”
2030-09-30; requested date only, not an achieved opening.
“"projectNumber":"J4152","queueDate":"2025-10-06T04:00:00+00:00","inService":"2030-09-30T04:00:00+00:00"”
Active; queue status does not establish physical construction or commercial service.
“"applicationStatus":"Active","sisPhase1":"","postGIAStatus":""”
Solar; Cedar Mountain - Lyon County 345.0kV.
“"fuelType":"Solar","facilityType":"Photovoltaic"”
Interconnection request received
“"projectNumber":"J4152","queueDate":"2025-10-06T04:00:00+00:00"”
Requested in-service date
“"projectNumber":"J4152","queueDate":"2025-10-06T04:00:00+00:00","inService":"2030-09-30T04:00:00+00:00"”
このピンはニュースを追い、最新の情報を表示しています。何が変わり、何がきっかけだったかをここに示します。
編集@ThePinGang による
MISO regional transmission interconnection development of the Cedar Mountain to Lyon County Clean Solar CenterJ4152 is a 250 MW photovoltaic generation interconnection request in Redwood County, Minnesota. Supplying 250 MWac of renewable power along the 345 kV transmission corridor, the facility accelerates Minnesota's transition toRedwood, MN. The grid operator lists its queue status as Active. The requested in-service date is 2030-09-30; this is a fully decarbonized electricity grid.planning date.
Xcel Energy filed site permit applications for the Cedar Mountain to Lyon County Clean Solar Center in Redwood County, Minnesota. Supplies 250 MWac of bifacial tracking photovoltaic capacity. RepresentsJ4152 is a 250 MW photovoltaic generation interconnection request in Redwood, MN. The grid operator lists its queue status as Active. The requested in-service date is 2030-09-30; this is a 270 million USD renewable infrastructure investment in southwestern Minnesota. Interconnects to the 345 kV regional transmission network within the MISO footprint. Supports Minnesota's statutory mandate for 100 percent carbon-free electricity by 2040. Timeline: planned project targeting commercial operation in September 2030 (estimated) under MISO interconnection queue and state regulatory schedules.planning date. The point of interconnection is Cedar Mountain - Lyon County 345.0kV. Queue processing status does not establish physical construction or commercial operation. No exact-scope construction budget is published in the cited grid record. Battery power is distinct from stored energy; no four-hour duration or battery MWh is inferred.
編集@ThePinGang による
… mandate for 100 percent carbon-free electricity by 2040. Timeline: planned project targeting commercial operation in September 2030 (estimated) under MISO interconnection queue and state regulatory schedules.
読者の写真で、出典付きのピンのメディアとは別に表示されます。食べたものや見たものを評価でき、レストランのピンでは写真上に料理をタグ付けできます。
最初の項目は常にピンの出典です。全体の確度は、各資料が上記の開始・終了時刻をどれだけ強く裏付けているかの加重平均です。最新の資料より180日古くなるごとに、重みは半分になります。
足りない点や誤りがありますか? このピンを裏付けるリンク、別の開始日・終了日とその理由、欠けている情報や誤っている情報を、自由に書いてください。AIがこのピンの出典と照らし合わせ、より良い情報源を探し、裏付けとなるページがあれば参考資料として追加します。ピン自身の出典が引き続き最も重視されます。AIは画像も確認します。別のものが写っている画像や写りの悪い画像は、後ろに回すか差し替えます。
元のタイトル: Cedar Mountain to Lyon County: 250 MW Solar Interconnection Request J4152
Power generation250 MW · J4152: 250 MW requested photovoltaic generation. Queue status: Active. Requested date: 2030-09-30. Not current measured generation; No annual energy or battery MWh inferred. · source