Energy: battery storage · 確認日 2026-10-30
確認された段階のみ強調しています。数値と日付は計画と実証済みを区別しています。
250 MW battery storage request; preliminary interconnection scope, not measured output.
“"poiName":"Wabaco","summerNetMW":250.0”
2030-06-30; requested date only, not an achieved opening.
“"projectNumber":"J3848","queueDate":"2024-12-31T05:00:00+00:00","inService":"2030-06-30T04:00:00+00:00"”
Active; queue status does not establish physical construction or commercial service.
“"applicationStatus":"Active","sisPhase1":"","postGIAStatus":""”
Battery Storage; Wabaco.
“"fuelType":"Battery Storage","facilityType":"Battery Storage"”
Interconnection request received
“"projectNumber":"J3848","queueDate":"2024-12-31T05:00:00+00:00"”
Requested in-service date
“"projectNumber":"J3848","queueDate":"2024-12-31T05:00:00+00:00","inService":"2030-06-30T04:00:00+00:00"”
このピンはニュースを追い、最新の情報を表示しています。何が変わり、何がきっかけだったかをここに示します。
編集@ThePinGang による
MISO regional transmission interconnection development of the Wabaco Clean Energy Storage Center in Wabasha County, Minnesota. SupplyingJ3848 is a 250 MW / 1,000 MWh of grid-scale battery storage along the Upper Mississippi River transmission corridor, the facility stores regional wind and solar generation to accelerate Minnesota's transition to 100% carbon-free electricity.interconnection request in Wabasha, MN. The grid operator lists its queue status as Active. The requested in-service date is 2030-06-30; this is a planning date.
Xcel Energy filed regulatory petitions for the Wabaco Clean Energy Storage CenterJ3848 is a 250 MW battery storage interconnection request in Wabasha County, Minnesota. Supplies 250 MW / 1,000 MWh of four-hour grid-scale battery storage capacity. Represents an estimated 250 million USD clean energy infrastructure investment. Interconnects with MISO high-voltage transmission lines along the Upper Mississippi River corridor. Captures regional wind and solar generation to accelerate Minnesota's statutory transition to 100% carbon-free electricity. Timeline: planned project targeting commercial operation in June 2030 (estimated) under MISO interconnection queue and state regulatory schedules.Wabasha, MN. The grid operator lists its queue status as Active. The requested in-service date is 2030-06-30; this is a planning date. The point of interconnection is Wabaco. Queue processing status does not establish physical construction or commercial operation. No exact-scope construction budget is published in the cited grid record. Battery power is distinct from stored energy; no four-hour duration or battery MWh is inferred.
編集@ThePinGang による
… accelerate Minnesota's statutory transition to 100% carbon-free electricity. Timeline: planned project targeting commercial operation in June 2030 (estimated) under MISO interconnection queue and state regulatory schedules.
読者の写真で、出典付きのピンのメディアとは別に表示されます。食べたものや見たものを評価でき、レストランのピンでは写真上に料理をタグ付けできます。
最初の項目は常にピンの出典です。全体の確度は、各資料が上記の開始・終了時刻をどれだけ強く裏付けているかの加重平均です。最新の資料より180日古くなるごとに、重みは半分になります。
足りない点や誤りがありますか? このピンを裏付けるリンク、別の開始日・終了日とその理由、欠けている情報や誤っている情報を、自由に書いてください。AIがこのピンの出典と照らし合わせ、より良い情報源を探し、裏付けとなるページがあれば参考資料として追加します。ピン自身の出典が引き続き最も重視されます。AIは画像も確認します。別のものが写っている画像や写りの悪い画像は、後ろに回すか差し替えます。
元のタイトル: Wabaco: 250 MW Battery Interconnection Request J3848
Power storage250 MW · J3848: 250 MW requested battery storage. Queue status: Active. Requested date: 2030-06-30. Not current measured generation; No annual energy or battery MWh inferred. · source