発表済み
Energy: photovoltaic generation · 確認日 2026-10-30
確認された段階のみ強調しています。数値と日付は計画と実証済みを区別しています。
199 MW photovoltaic generation request; preliminary interconnection scope, not measured output.
“"poiName":"Robinsonville 230 kV","summerNetMW":199.0”
2024-12-01; requested date only, not an achieved opening.
“"projectNumber":"J2047","queueDate":"2021-08-12T04:00:00+00:00","inService":"2024-12-01T05:00:00+00:00"”
Done; queue status does not establish physical construction or commercial service.
“"applicationStatus":"Done","sisPhase1":"","postGIAStatus":"Not Started"”
Solar; Robinsonville 230 kV.
“"fuelType":"Solar","facilityType":"Photovoltaic"”
Interconnection request received
“"projectNumber":"J2047","queueDate":"2021-08-12T04:00:00+00:00"”
Requested in-service date
“"projectNumber":"J2047","queueDate":"2021-08-12T04:00:00+00:00","inService":"2024-12-01T05:00:00+00:00"”
このピンはニュースを追い、最新の情報を表示しています。何が変わり、何がきっかけだったかをここに示します。
編集@ThePinGang による
Tennessee Valley Authority (TVA) transmission-interconnected development of the Robinsonville Clean Solar CenterJ2047 is a 199 MW photovoltaic generation interconnection request in DeSoto County, Mississippi. Delivering 199 MWac of clean photovoltaic power, the facility ties to the 230 kV electric grid to provide zero-carbon electricity to northwestern Mississippi communities and commercial developments.DeSoto, MS. The grid operator lists its queue status as Done. The requested in-service date is 2024-12-01; this is a planning date.
The Tennessee Valley Authority (TVA) progressed environmental assessments for the Robinsonville Clean Solar Center in DeSoto County, Mississippi. Deploys 199 MWac of clean photovoltaic power across northwest Mississippi. RepresentsJ2047 is a 199 MW photovoltaic generation interconnection request in DeSoto, MS. The grid operator lists its queue status as Done. The requested in-service date is 2024-12-01; this is a 220 million USD clean energy infrastructure investment. Interfaces directly with theplanning date. The point of interconnection is Robinsonville 230 kV electric grid along the US Highway 61 corridor. Supplies zero-carbon electricity to regional communities and growing commercial developments. Timeline: planned project targeting commercial operation in December 2027 (estimated) under regional grid interconnection queue and state regulatory schedules.kV. Queue processing status does not establish physical construction or commercial operation. No exact-scope construction budget is published in the cited grid record. Battery power is distinct from stored energy; no four-hour duration or battery MWh is inferred.
編集@ThePinGang による
… electricity to regional communities and growing commercial developments. Timeline: planned project targeting commercial operation in December 2027 (estimated) under regional grid interconnection queue and state regulatory schedules.
編集@ThePinGang による
読者の写真で、出典付きのピンのメディアとは別に表示されます。食べたものや見たものを評価でき、レストランのピンでは写真上に料理をタグ付けできます。
最初の項目は常にピンの出典です。全体の確度は、各資料が上記の開始・終了時刻をどれだけ強く裏付けているかの加重平均です。最新の資料より180日古くなるごとに、重みは半分になります。
足りない点や誤りがありますか? このピンを裏付けるリンク、別の開始日・終了日とその理由、欠けている情報や誤っている情報を、自由に書いてください。AIがこのピンの出典と照らし合わせ、より良い情報源を探し、裏付けとなるページがあれば参考資料として追加します。ピン自身の出典が引き続き最も重視されます。AIは画像も確認します。別のものが写っている画像や写りの悪い画像は、後ろに回すか差し替えます。
元のタイトル: Robinsonville: 199 MW Solar Interconnection Request J2047
Power generation199 MW · J2047: 199 MW requested photovoltaic generation. Queue status: Done. Requested date: 2024-12-01. Not current measured generation; No annual energy or battery MWh inferred. · source