Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · 出典
Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · 出典
Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · 出典
| Date | Observed status |
|---|---|
| 2022-04-14 | Land clearing begins for Building 1-2 |
| 2025-06-01 | Roof complete on Building 5 (QTS-owned). In the northernmost area, land clearing begins on a new Meta site for Buildings 16-20. Building 1 still has construction work around the building and cooling e |
| 2025-09-20 | Building 4 operational. Based on our default estimate of roof-to-operational time. |
| 2025-10-14 | Building 1 is operational, based on there being minimal construction work and cars in the main carpark. Building 2 still has some construction work around the building. Building 18 roof is complete. T |
| 2026-01-18 | Buildings 2-6 are operational, based on all equipment being in place, the paved ground, and minimal construction equipment by the buildings. Buildings 7-11 all have some kind of power or cooling equip |
| 2026-03-12 | The Socrates South power plant to the right of Buildings 7-12 now has 10 natural gas turbines in place, judging by the number of exhaust stacks. Battery backup has been installed nearby. To the north, |
| 2026-05-18 | Building 7-11 (Meta tents) look structurally complete but not operational, given there is still construction activity, including at the adjacent Socrates South power plant. Northern tents (Buildings 1 |
| 2026-08-31 | Buildings 7-10 (tents) are operational, based on infrared drone video from RAAD (raad.com) captured on this date. The video suggests that 138.8 MW of nameplate turbine capacity is operating at the Soc |
| 2026-11-30 | Socrates South and Socrates North gas power plants are fully operational, enabling the operability of Buildings 11-12 and 16-21. This completes the 2 sets of 6 tents associated with Socrates South and |
| 2027-01-15 | Building 13 (Vantage) is operational, based on the pace of construction seen in earlier images. |
| 2027-04-15 | Building 14 (Vantage) is operational, based on it starting construction about 3 months after Building 13. |
| 2027-07-14 | Building 15 (Vantage) operational, based on it starting construction about 3 months after Building 14. |
| 2028-07-01 | Buildings 22-27 (3rd set of 6 Meta tents) are operational. This is a conservative estimate to align with the operability of the [Socrates the Younger](https://drive.google.com/file/d/1Gqu84nBqkyrrwMQy |
Epoch AI satellite-imagery notes, in date order. · 出典
建設中
Digital infrastructure: AI data-center campus buildout · 確認日 2026-10-30
確認された段階のみ強調しています。数値と日付は計画と実証済みを区別しています。
Epoch’s current campus estimate: 471 MW IT power. This is modeled total campus context, not measured draw, a utility allocation or the remaining phase’s incremental rating.
“CURRENT IT POWER 471 MW”
Physical-stage observation dated 2026-08-31. Campus buildout remains under construction; already operating buildings do not complete the remaining work. Forecast operational dates retain the directory’s uncertainty and do not establish actual completion.
“Building 13 (Vantage) is still under construction”
Epoch’s dated 2026-08-31 assessment: Building 13 (Vantage) is still under construction Campus buildout remains under construction; already operating buildings do not complete the remaining work.
“Building 13 (Vantage) is still under construction”
Epoch estimates AI hardware: Nvidia B300 chips. Chip fit-out is directory research, not operator-certified inventory.
“We estimate that it uses Nvidia B300 chips.”
Epoch dated observation: Land clearing begins for Building 1-2
“Land clearing begins for Building 1-2”
Epoch dated observation: Buildings 7-10 (tents) are operational, based on infrared drone video…
“Buildings 7-10 (tents) are operational, based on infrared drone video from RAAD (raad.com) captured on this date.”
読者の写真で、出典付きのピンのメディアとは別に表示されます。食べたものや見たものを評価でき、レストランのピンでは写真上に料理をタグ付けできます。
最初の項目は常にピンの出典です。全体の確度は、各資料が上記の開始・終了時刻をどれだけ強く裏付けているかの加重平均です。最新の資料より180日古くなるごとに、重みは半分になります。
保存された日付は、推定された追跡または容量の軌道マーカーであり、検証された正確な開設日ではありません。 建設ステータスは、引用された日付の物理的範囲に従います。 経過目標から完了は推測されません。
Construction research 2026-10-24: Epoch’s[1] 2026-08-31 observation documents remaining physical construction/installation for this named buildout. In Progress does not complete earlier operating buildings or future capacity. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget. Source quote: “Building 13 (Vantage) is still under construction” Dated observation 2026-08-31; future trajectory rows and modeled costs are distinguished from this physical milestone.
足りない点や誤りがありますか? このピンを裏付けるリンク、別の開始日・終了日とその理由、欠けている情報や誤っている情報を、自由に書いてください。AIがこのピンの出典と照らし合わせ、より良い情報源を探し、裏付けとなるページがあれば参考資料として追加します。ピン自身の出典が引き続き最も重視されます。AIは画像も確認します。別のものが写っている画像や写りの悪い画像は、後ろに回すか差し替えます。
元のタイトル: Meta Prometheus AI Data Center Buildout
米国オハイオ州ニュー アルバニーにある Meta Prometheus は、Meta が運営するフロンティア AI データ センター キャンパスで、電力容量 1,022 MW に達し、H100 相当の AI アクセラレータ 1,164,337 台を備えています。 メタ プロメテウスは、ニュー アルバニー ビジネス パークの全長に広がる耐候性のテント、コロケーション施設、伝統的なデータ センターの建物のパッチワークという、アドホックな構造が特徴です。
エポック社の 2026 年 8 月 31 日の観察では、この名前付きビルドアウトの残りの物理的な建設/設置が記録されています。 「進行中」は、以前に稼働中の建物や将来の容量を完成させるものではありません。 パワーとアクセル数はエポック社の推定値のままであり、オペレーターが認定した評価値ではありません。 モデル化された 2025 ドルの資本コストにはコンピューティング ハードウェアが含まれており、ソースネイティブの建設予算ではありません。