Construction research 2026-10-24: Epoch’s[1] 2026-07-30 observation documents remaining physical construction/installation for this named buildout. In Progress does not complete earlier operating buildings or future capacity. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget. Source quote: “still under construction and not yet energized” Dated observation 2026-07-30; future trajectory rows and modeled costs are distinguished from this physical milestone.
San Angelo LIVE! confirms the 951 County Road 204 site, Cipher/Fluidstack/Anthropic partnership, and $10M municipal water foundation pledge.
TheEnergyMag reports Barber Lake's 10-year ~$3B Fluidstack lease for 168 MW (with $1.4B Google backstop) and off-grid on-site water supply.
足りない点や誤りがありますか? このピンを裏付けるリンク、別の開始日・終了日とその理由、欠けている情報や誤っている情報を、自由に書いてください。AIがこのピンの出典と照らし合わせ、より良い情報源を探し、裏付けとなるページがあれば参考資料として追加します。ピン自身の出典が引き続き最も重視されます。AIは画像も確認します。別のものが写っている画像や写りの悪い画像は、後ろに回すか差し替えます。
| 1 号棟の基礎が見えます。 |
| 2026-07-30 | 建物 1 のシェルは完成し、屋上ユニットが設置され、ほとんどの空冷チラーが北の地上ヤードに設置されました。120 台の予備ディーゼル発電機のほとんども設置されています。実質的な |
|---|
| 2026-12-30 | ビル 1 フェーズ I は稼働中です。重要な IT 電力は 168 MW (総計 244 MW)、Google TPU v7 を実行しています (チップ タイプは推定、タグ付けされている可能性があります)。公表された時期より約 3 か月遅れ、2026 年 12 月までと予想しています。 |
|---|
| 2027-04-30 | ビル 1 フェーズ II は稼働中です。クリティカル IT の総容量は 207 MW (総計 300 MW)。フェーズ II では、39 MW の重要な IT が追加されます ([Cipher 2025-11-20 PR](https://www.globenewswire.com/news-release/2025/11/20/3191801/0) を参照) |
|---|
Epoch AI 衛星画像の日付順のメモ。 · 出典
Physical-stage observation dated 2026-07-30. Campus buildout remains under construction; already operating buildings do not complete the remaining work. Forecast operational dates retain the directory’s uncertainty and do not establish actual completion.
“still under construction and not yet energized”
Epoch’s dated 2026-07-30 assessment: still under construction and not yet energized Campus buildout remains under construction; already operating buildings do not complete the remaining work.
“still under construction and not yet energized”
AI data-center compute infrastructure. Hardware inventory remains unpublished or not verified in this project assessment.
“AI data center”
Epoch dated observation: Site grading and civil works begin.
“Site grading and civil works begin.”
Epoch dated observation: Building 1 shell is complete, with rooftop units installed, and most…
“Building 1 shell is complete, with rooftop units installed, and most air-cooled chillers in place in a ground yard to the north.”
元のタイトル: Anthropic Barber Lake AI Data Center Buildout
米国テキサス州コロラド市にある Anthropic Barber Lake は、Cipher Mining / Anthropic が運営するフロンティア AI データ センター キャンパスで、207 MW の電力容量と 288,530 個の H100 相当の AI アクセラレータを備えています。 Barber Lake は、NVIDIA GPU ではなく Google TPU を実行しています。Google はチップの供給と構築の資金調達を支援し、そのシリコンが Fluidstack を通じて Anthropic に展開できるように開発者の株式を取得しました。
エポック社の 2026 年 7 月 30 日の観察では、この名前付きのビルドアウトの残りの物理的な建設/設置が記録されています。 「進行中」は、以前に稼働中の建物や将来の容量を完成させるものではありません。 パワーとアクセル数はエポック社の推定値のままであり、オペレーターが認定した評価値ではありません。 モデル化された 2025 ドルの資本コストにはコンピューティング ハードウェアが含まれており、ソースネイティブの建設予算ではありません。