Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · 出典
Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · 出典
Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · 出典
| Date | Observed status |
|---|---|
| 2024-11-01 | Land clearing begins. |
| 2026-02-14 | Buildings 1 and 2 under construction. Building 1's chillers are almost all in place, while only half of Building 2's are. Optimus substation, which is the substation on site, and the expansion of Dowl |
| 2026-07-30 | Roofs of Buildings 1 and 2 are more than halfway complete. All chillers for both buildings are visible. Construction on Buildings 3 and 4 has begun, with outlines laid. Construction on the [Apollo Pow |
| 2027-02-01 | Building 1 is operational, based on a 5 month extrapolation from its roof completion date. |
| 2027-04-01 | Building 2 is operational, based on construction progress as of Sep 2026 and foundations being laid around 2 months after Building 1. |
| 2028-01-01 | Buildings 3 and 4 are operational, based on their construction starting 11 months after Building 1. We assume they are powered by the 350 MW Apollo Power Generation Project. |
Epoch AI satellite-imagery notes, in date order. · 出典
建設中
Digital infrastructure: AI data-center campus buildout · 確認日 2026-10-30
確認された段階のみ強調しています。数値と日付は計画と実証済みを区別しています。
Epoch’s current campus estimate: 0 MW IT power. This is modeled total campus context, not measured draw, a utility allocation or the remaining phase’s incremental rating.
“CURRENT IT POWER 0 MW”
Physical-stage observation dated 2026-07-30. Campus buildout remains under construction; already operating buildings do not complete the remaining work. Forecast operational dates retain the directory’s uncertainty and do not establish actual completion.
“Construction on Buildings 3 and 4 has begun”
Epoch’s dated 2026-07-30 assessment: Construction on Buildings 3 and 4 has begun Campus buildout remains under construction; already operating buildings do not complete the remaining work.
“Construction on Buildings 3 and 4 has begun”
AI data-center compute infrastructure. Hardware inventory remains unpublished or not verified in this project assessment.
“AI data center”
Epoch dated observation: Land clearing begins.
“Land clearing begins.”
Epoch dated observation: Roofs of Buildings 1 and 2 are more than halfway complete.
“Roofs of Buildings 1 and 2 are more than halfway complete.”
読者の写真で、出典付きのピンのメディアとは別に表示されます。食べたものや見たものを評価でき、レストランのピンでは写真上に料理をタグ付けできます。
最初の項目は常にピンの出典です。全体の確度は、各資料が上記の開始・終了時刻をどれだけ強く裏付けているかの加重平均です。最新の資料より180日古くなるごとに、重みは半分になります。
保存された日付は、推定された追跡または容量の軌道マーカーであり、検証された正確な開設日ではありません。 建設ステータスは、引用された日付の物理的範囲に従います。 経過目標から完了は推測されません。
Construction research 2026-10-24: Epoch’s[1] 2026-07-30 observation documents remaining physical construction/installation for this named buildout. In Progress does not complete earlier operating buildings or future capacity. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget. Source quote: “Construction on Buildings 3 and 4 has begun” Dated observation 2026-07-30; future trajectory rows and modeled costs are distinguished from this physical milestone.
足りない点や誤りがありますか? このピンを裏付けるリンク、別の開始日・終了日とその理由、欠けている情報や誤っている情報を、自由に書いてください。AIがこのピンの出典と照らし合わせ、より良い情報源を探し、裏付けとなるページがあれば参考資料として追加します。ピン自身の出典が引き続き最も重視されます。AIは画像も確認します。別のものが写っている画像や写りの悪い画像は、後ろに回すか差し替えます。
元のタイトル: Meta Bowling Green AI Data Center Buildout
米国オハイオ州ボウリング グリーンにある Meta Bowling Green は、Meta が運営するフロンティア AI データ センター キャンパスで、電力容量 422 MW に達し、H100 相当の AI アクセラレータ 855,159 台を備えています。 0
エポック社の 2026 年 7 月 30 日の観察では、この名前付きのビルドアウトの残りの物理的な建設/設置が記録されています。 「進行中」は、以前に稼働中の建物や将来の容量を完成させるものではありません。 パワーとアクセル数はエポック社の推定値のままであり、オペレーターが認定した評価値ではありません。 モデル化された 2025 ドルの資本コストにはコンピューティング ハードウェアが含まれており、ソースネイティブの建設予算ではありません。