Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · 出典
Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · 出典
Epoch AI's modelled estimates from satellite imagery, permits and company statements; dates after today are Epoch's projections. · 出典
| Date | Observed status |
|---|---|
| 2024-05-31 | Land clearing begins for northern two buildings (Building 1-2) |
| 2025-06-28 | Building 1 looks close to finishing construction, with chillers in place. OpenAI [stated](https://openai.com/index/five-new-stargate-sites/) that "Oracle began delivering the first NVIDIA GB200 racks |
| 2025-09-26 | Building 1 is fully operational around this date. The first phase was "live" on September 30 according a Crusoe [announcement](https://www.crusoe.ai/resources/newsroom/crusoe-announces-flagship-abilen |
| 2025-12-24 | Building 2 is fully operational. This exact date corresponds to the expected completion date of "Four (4) data hall spaces and an administrative office build-out" according to a [TDLR filing](https:// |
| 2026-01-15 | The 1 GW substation looks close to completion. Building 3 appears to have all power and cooling equipment installed, but there are still signs of construction work. This seems on track for operation i |
| 2026-03-24 | Building 3 and 4 look complete, but are not fully operational. Not as many cars are parked next to it as Building 1-2 which suggests they may still be ramping up. Building 4 was due by now according t |
| 2026-05-23 | Buildings 3 and 4 are estimated to be operational. On April 22nd, Oracle [posted](https://x.com/i/status/2047012589302153558) that "In Abilene, 200MW is already operational". This suggests that there |
| 2026-07-28 | Buildings 5-8 are structurally complete and roofed but not yet confirmed operational (fit-out ongoing). The substation looks complete. |
| 2026-09-10 | Buildings 5-6 are operational. On Oracle's Q1 FY27 earnings call (September 10, 2026), Clay Magouyrk said "6 of the 8 campus buildings, representing 618 megawatts and 75% of total capacity have now be |
| 2026-11-01 | Buildings 7-8 are estimated to be operational. On March 24, Building 8 roughly looked like where Building 3 was in September. Building 3 is estimated to be operational in April, 7 months later. This n |
Epoch AI satellite-imagery notes, in date order. · 出典
建設中
Data center · 確認日 2026-10-31
確認された段階のみ強調しています。数値と日付は計画と実証済みを区別しています。
$15 billion
“announced the second phase of a $15 billion joint venture to fund the campus.”
About 4 million sq ft, eight buildings
“bringing the campus to eight buildings, about 4 million square feet and 1.2 gigawatts”
875 acres
“sits Stargate — an 875-acre AI data center campus”
618 MW delivered of 824 MW IT projected (Epoch); campus 1.2 GW grid-level design
“said six of the eight buildings, representing 618 megawatts and 75 percent of the campus, had been delivered”
Six of eight buildings delivered; Buildings 7-8 fit-out
“Buildings 5-6 are operational.”
Land clearing begins for Buildings 1-2 (Epoch satellite observation)
“Land clearing begins for northern two buildings (Building 1-2)”
City council approves 85%, 10-year tax abatements
“The Abilene City Council approved 85 percent, 10-year property tax abatements for the site in February 2025”
Second phase of six more buildings announced (eight total, 1.2 GW)
We got taken, we got robbed,
So were there things we could have done different? Of course there were,
Who exactly is paying for all of this?
come to Abilene every day to build the future of AI infrastructure
読者の写真で、出典付きのピンのメディアとは別に表示されます。食べたものや見たものを評価でき、レストランのピンでは写真上に料理をタグ付けできます。
最初の項目は常にピンの出典です。全体の確度は、各資料が上記の開始・終了時刻をどれだけ強く裏付けているかの加重平均です。最新の資料より180日古くなるごとに、重みは半分になります。
始まりは、エポック社の衛星観測による土地の開墾です。クルーソー氏は、建設は2024年6月に始まったと述べている。エポック社によるビル7~8の稼働予定は2026年11月である。開発者の日付は公開されていません。
Cited in the project timeline.[1]
Construction research 2026-10-24: Epoch’s[1][7] 2026-07-28 observation documents remaining physical construction/installation for this named buildout. In Progress does not complete earlier operating buildings or future capacity. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget. Source quote: “not yet confirmed operational” Dated observation 2026-07-28; future trajectory rows and modeled costs are distinguished from this physical milestone.
Cited in the project timeline.[1]
足りない点や誤りがありますか? このピンを裏付けるリンク、別の開始日・終了日とその理由、欠けている情報や誤っている情報を、自由に書いてください。AIがこのピンの出典と照らし合わせ、より良い情報源を探し、裏付けとなるページがあれば参考資料として追加します。ピン自身の出典が引き続き最も重視されます。AIは画像も確認します。別のものが写っている画像や写りの悪い画像は、後ろに回すか差し替えます。
元のタイトル: OpenAI Stargate Abilene AI Data Center Buildout
テキサス州アビリーンにある OpenAI の Stargate キャンパスは、Crusoe が Oracle にリースした 8 棟の建物、約 400 万平方フィート、1.2 GW の開発施設です。建設は 2024 年に始まりました。Oracle は、8 棟のうち 6 棟が 2026 年 9 月 10 日に引き渡され、最後の 2 棟はまだ設備工事中であると報告しました。150 億ドルの合弁事業がキャンパスに資金を提供しています。Epoch AI は、現在 618 MW、完成時には 824 MW の IT 電力を見積もっています。
エポック社の 2026 年 7 月 28 日の観察では、この名前付きビルドアウトの残りの物理的な建設/設置が記録されています。 「進行中」は、以前に稼働中の建物や将来の容量を完成させるものではありません。 パワーとアクセル数はエポック社の推定値のままであり、オペレーターが認定した評価値ではありません。 モデル化された 2025 ドルの資本コストにはコンピューティング ハードウェアが含まれており、ソースネイティブの建設予算ではありません。
注釈付きの衛星フットプリント (70 個の物理部品) を使用して Epoch AI によって追跡されるハイパースケール フロンティア AI トレーニングおよび推論キャンパス。
“announced a second phase of six more buildings, bringing the campus to eight buildings, about 4 million square feet and 1.2 gigawatts”
$15 billion Crusoe/Blue Owl/Primary Digital joint venture announced for the campus
“On May 21, 2025, Crusoe, Blue Owl Capital and Primary Digital Infrastructure announced the second phase of a $15 billion joint venture to fund the campus.”
Buildings 1-2 live on Oracle Cloud Infrastructure
“Crusoe said on Sept. 30, 2025, that the first phase was running on Oracle Cloud Infrastructure”
Crusoe tops out the eighth and final building
“Crusoe has marked a major milestone in its AI infrastructure expansion by topping out the eighth and final building”
Building 2 fully operational (Epoch estimate; matches TDLR completion date)
“Building 2 is fully operational.”
OpenAI and Oracle drop plan to expand Abilene beyond about 1.2 GW
“OpenAI had planned to expand this site to 2.1 GW, but recently reversed course”
Buildings 5-8 structurally complete and roofed; fit-out ongoing
“Buildings 5-8 are structurally complete and roofed but not yet confirmed operational (fit-out ongoing).”
Oracle: six of eight buildings, 618 MW, delivered
“said six of the eight buildings, representing 618 megawatts and 75 percent of the campus, had been delivered”
Buildings 7-8 estimated operational (full campus; Oracle gave no date)
“Buildings 7-8 are estimated to be operational.”