The saved date is an estimated tracking or capacity-trajectory marker, not a verified exact opening day. Construction status follows the cited dated physical scope; no completion is inferred from elapsed targets.
Construction research 2026-10-24: Epoch’s[1] 2026-06-13 observation documents remaining physical construction/installation for this named buildout. In Progress does not complete earlier operating buildings or future capacity. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget. Source quote: “all the yard work directly surrounding it” Dated observation 2026-06-13; future trajectory rows and modeled costs are distinguished from this physical milestone.
足りない点や誤りがありますか? このピンを裏付けるリンク、別の開始日・終了日とその理由、欠けている情報や誤っている情報を、自由に書いてください。AIがこのピンの出典と照らし合わせ、より良い情報源を探し、裏付けとなるページがあれば参考資料として追加します。ピン自身の出典が引き続き最も重視されます。AIは画像も確認します。別のものが写っている画像や写りの悪い画像は、後ろに回すか差し替えます。
| 2026-06-13 | 衛星画像によると、ビル 1 は建設を完了しており、変電所/発電機が設置されると想定される隣接する土地は整地されています。ビル 1 は稼働していないと考えられます。 |
|---|
| 2026-12-31 | 現在完成している建物と南西にある完成した変電所から判断すると、建物 1 は年末までに稼働すると推定されます。周囲の庭工事・工事は |
|---|
| 2027-12-31 | Core Scientific[4] は、2 番目の未リースの 82.5 MW マスコギー ビルの初回引き渡しを 2027 年第 4 四半期に予定しています。現時点では CoreWeave GPU を搭載する契約は締結されていませんが、将来変更される可能性があります。出典: https://www.se |
|---|
Epoch AI 衛星画像の日付順のメモ。 · 出典
Physical-stage observation dated 2026-06-13. Campus buildout remains under construction; already operating buildings do not complete the remaining work. Forecast operational dates retain the directory’s uncertainty and do not establish actual completion.
“all the yard work directly surrounding it”
Epoch’s dated 2026-06-13 assessment: all the yard work directly surrounding it Campus buildout remains under construction; already operating buildings do not complete the remaining work.
“all the yard work directly surrounding it”
AI data-center compute infrastructure. Hardware inventory remains unpublished or not verified in this project assessment.
“AI data center”
Epoch dated observation: Core Scientific, CoreWeave, and Port Muskogee publicly announce…
“Core Scientific, CoreWeave, and Port Muskogee publicly announce groundbreaking for the 100 MW Muskogee HPC data center.”
Epoch assessment: Based on satellite imagery, Building 1 has completed construction, with…
“Based on satellite imagery, Building 1 has completed construction, with adjacent land cleared for what we're assuming will have power substations/generators.”
Epoch’s 2026-06-13 observation documents remaining physical construction/installation for this named buildout. In Progress does not complete earlier operating buildings or future capacity. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget.
Hyperscale frontier AI training and inference campus tracked by Epoch AI with annotated satellite footprints (6 physical parts).