Sizewell C Begins Generating
- Sizewell C is a two-unit EPR nuclear station (2 x 1,630 MWe, about 3.2 GW) in Suffolk next to Sizewell B, a near-copy of Hinkley Point C, expected to power about six million homes for at least 60 years[1][2][3]
- Final investment decision was signed 22 July 2025; stakes are UK Government 44.9%, La Caisse 20%, Centrica 15%, EDF 12.5% and Amber Infrastructure 7.6%[1][3]
- Cost is expected at GBP 38 billion as of July 2025, with the National Wealth Fund providing the majority of debt; nearly double EDF's earlier forecast of about GBP 20 billion; bills rise by an average GBP 1 a month during construction[1][3]
- Timeline: Miliband said mid-2034 for operation and the company's lawyer said both reactors operational by mid-2034; EDF said in 2023 the earliest one reactor could run is end of 2033, so the pin's 2035 estimate is later than these[3]
- Construction formally began 15 January 2024; in January 2025 the project reported being on time and on budget with GBP 1 billion of savings from replicating Hinkley Point C[1][2]
- Opposition includes Together Against Sizewell C and the RSPB over wildlife impact near Minsmere[1][3]
References 361% CONFIDENCE
The first entry is always the pin's source. Overall confidence is a weighted average of how firmly each reference supports the start and end times used above; a reference counts half as much for every 180 days older than the newest.
- [1]50%en.wikipedia.org/wiki/Sizewell_C_nuclear_power_stationen.wikipedia.org· Posted Sep 11, 2026· Starts Jun 1, 2035 ✓· 57% of score
Given as a target, not a fixed date, per the pin description: "…C intended to power six million homes. Estimated date.…"
- [2]78%Sizewell C reports project progress to parliamentworld-nuclear-news.org· Published Jan 1, 2026· 21% of score
World Nuclear News, the nuclear trade press, reports Sizewell C's official progress update; EDF's own best-case estimate is first power by end-2033 with both reactors operational by mid-2034, roughly consistent with the pin's mid-2030s stored date.
- [3]74%How long will it take for Sizewell C power station to make energy bills lower?uk.news.yahoo.com· Published Jan 1, 2026· 21% of score
Corroborates EDF's stated best-case scenario that the earliest either reactor could be operational is end of 2033, with full output by mid-2034.[1]
Suggest a correction
Something missing or wrong? Say it in your own words: a link that backs this pin up, a different start or end date and why, or a fact it lacks or gets wrong. The AI checks it against this pin's sources, searches for better ones, and adds any page that backs you up. The pin's own sources still count most.