情報源によれば、予定どおりに行われます:「2027 年初頭に計画」。
Member states, 2013 baseline cost 1.843bn euros, ERIC status, instrument list and site.[1]
The B1M, a well-regarded engineering/construction video outlet, covers the European Spallation Source project described in the pin, but as a secondary explainer rather than an ESS[4] statement its confirmation is weaker, and the page content could not be retrieved (domain blocked) to confirm the 2027 date.
ESS's own official site, published 7 July 2026, headlines progress "advancing toward first neutrons," directly backing the pin's "planned for early 2027" claim as the primary institutional source, though the article text could not be retrieved (domain blocked).
Describes 2026 status: moderator damage from late-2025 power dip, Q4 2026 replacement, instrument readiness, construction start 2014, user programme timing.[1]
足りない点や誤りがありますか? このピンを裏付けるリンク、別の開始日・終了日とその理由、欠けている情報や誤っている情報を、自由に書いてください。AIがこのピンの出典と照らし合わせ、より良い情報源を探し、裏付けとなるページがあれば参考資料として追加します。ピン自身の出典が引き続き最も重視されます。AIは画像も確認します。別のものが写っている画像や写りの悪い画像は、後ろに回すか差し替えます。
元のタイトル: European Spallation Source Aims for First Neutrons