The first entry is always the pin's source. Overall confidence is a weighted average of how firmly each reference supports the start and end times used above; a reference counts half as much for every 180 days older than the newest.
Published target: End of 2027. Construction is documented, but this future completion/operation milestone is estimated. The date is a year/month-end timeline marker and is not a confirmed exact opening day. Source: https://www.sec[3].gov/Archives/edgar/data/1376986/000137698625000056/tve-20250930.htm
Kingston Energy Complex site construction, published March 6, 2025 alongside a TVA construction announcement. The image covers the wider energy complex, including the combined-cycle and aeroderivative work; it is not a photograph of a completed replacement plant.[1]
TVA FY2025 Form 10-K publishes $1.8 billion spent and $1.1 billion expected additional spending on the 1,500 MW Kingston combined-cycle plant as of September 30, 2025. Their sum is approximately $2.9 billion. This total is arithmetic on disclosed project amounts, not a benchmark estimate. Battery RFPs, proposed expansions and the wider campus rating are not included. Kingston combined-cycle replacement plant: published generating capacity 1500 MW. Operator-reported electric generating capacity; not annual energy production TVA explicitly states it is constructing the 1,500 MW combined-cycle plant, targeting the end of 2027. The capacity is for the combined-cycle plant, not all units at the Kingston site.[1]
Something missing or wrong? Say it in your own words: a link that backs this pin up, a different start or end date and why, or a fact it lacks or gets wrong. The AI checks it against this pin's sources, searches for better ones, and adds any page that backs you up. The pin's own sources still count most. A picture that shows something else, or shows it badly, is looked at too, and moved down or replaced.
Site construction underway as reported March 6, 2025.
“Site construction is underway”
Combined-cycle natural-gas technology within the wider Kingston Energy Complex.
“combined cycle natural gas plant”
Site construction reported
“March 6, 2025”
End of 2027. TVA’s FY2025 filing identifies physical construction of the 1,500 MW Kingston combined-cycle replacement plant and expected operation by the end of calendar 2027.[3]
Construction is verified; the completion date remains an estimate. The timeline marker represents the published target year/month, not a confirmed opening day.
TVA FY2025 Form 10-K publishes $1.8 billion spent and $1.1 billion expected additional spending on the 1,500 MW Kingston combined-cycle plant as of September 30, 2025. Their sum is approximately $2.9 billion. This total is arithmetic on disclosed project amounts, not a benchmark estimate. Battery RFPs, proposed expansions and the wider campus rating are not included.[3]
TVA FY2025 Form 10-K publishes $1.8 billion spent and $1.1 billion expected additional spending on the 1,500 MW Kingston combined-cycle plant as of September 30, 2025. Their sum is approximately $2.9 billion. This total is arithmetic on disclosed project amounts, not a benchmark estimate. Battery RFPs, proposed expansions and the wider campus rating are not included. Kingston combined-cycle replacement plant: published generating capacity 1500 MW. Operator-reported electric generating capacity; not annual energy production TVA explicitly states it is constructing the 1,500 MW combined-cycle plant, targeting the end of 2027. The capacity is for the combined-cycle plant, not all units at the Kingston site.[3]
Retained only with documented physical construction, commissioning or 2025–2026 opening and published project-specific costs and electrical output. Costs use the published scope and currency; no benchmark estimates or currency conversions. MW is power capacity, not annual electricity production. Expected annual energy, where given, is a forecast. The map point is a reported plant/project location and may be approximate. Matching inventory views and excluded expansion proposals are not additive capacity.
Kingston Energy Complex site construction, published March 6, 2025 alongside a TVA construction announcement. The image covers the wider energy complex, including the combined-cycle and aeroderivative work; it is not a photograph of a completed replacement plant. Credit: Tennessee Valley Authority announcement via 3B Media News; photographer not identified. Source and gallery; original media.
Power generation750 MW · Status: construction. 750 MW combined-cycle replacement plant; separate 800 MW aeros, storage and solar are excluded from this unit capacity. · source