Globeleq[3][4] December 28, 2023 publishes a US$117 million project investment for its 35 MW Menengai plant. This later figure supersedes the June 2023 US$108 million announcement. Other developers’ Menengai plants and the inventory’s broader 70 MW grouping are excluded. Globeleq Menengai geothermal plant: published generating capacity 35 MW. Operator-reported electric generating capacity; not annual energy production
Globeleq[2][4] verifies groundbreaking June 8, 2023. Its Kenya sustainability report describes the 35 MW plant in construction; August 2026 inventory still reports construction. Historical 2025 operation target is not asserted as completed.
The operator report confirms this 35 MW power plant in construction.[1]
Something missing or wrong? Say it in your own words: a link that backs this pin up, a different start or end date and why, or a fact it lacks or gets wrong. The AI checks it against this pin's sources, searches for better ones, and adds any page that backs you up. The pin's own sources still count most. A picture that shows something else, or shows it badly, is looked at too, and moved down or replaced.
35 MW geothermal generation for this plant, excluding other Menengai developers.
Original 2025 operation forecast remains unverified; no completion inferred.
Groundbreaking
Financial close
Globeleq December 28, 2023 publishes a US$117 million project investment for its 35 MW Menengai plant. This later figure supersedes the June 2023 US$108 million announcement. Other developers’ Menengai plants and the inventory’s broader 70 MW grouping are excluded.[2][3][4]
Globeleq December 28, 2023 publishes a US$117 million project investment for its 35 MW Menengai plant. This later figure supersedes the June 2023 US$108 million announcement. Other developers’ Menengai plants and the inventory’s broader 70 MW grouping are excluded. Globeleq Menengai geothermal plant: published generating capacity 35 MW. Operator-reported electric generating capacity; not annual energy production[2]
Globeleq verifies groundbreaking June 8, 2023. Its Kenya sustainability report describes the 35 MW plant in construction; August 2026 inventory still reports construction. Historical 2025 operation target is not asserted as completed.[3]
The operator report confirms this 35 MW power plant in construction.[4]
Retained only with documented physical construction, commissioning or 2025–2026 opening and published project-specific costs and electrical output. Costs use the published scope and currency; no benchmark estimates or currency conversions. MW is power capacity, not annual electricity production. Expected annual energy, where given, is a forecast. The map point is a reported plant/project location and may be approximate. Matching inventory views and excluded expansion proposals are not additive capacity.
Globeleq Menengai project groundbreaking ceremony, published July 2023. Credit: Globeleq; individual photographer not named. Source and gallery; original media.
Power generation35 MW · Status: construction. 35 MW geothermal generation for this plant, excluding other Menengai developers. Original 2025 operation forecast remains unverified; no completion inferred. · source