The first entry is always the pin's source. Overall confidence is a weighted average of how firmly each reference supports the start and end times used above; a reference counts half as much for every 180 days older than the newest.
Documented physical milestone or dated progress/reporting marker. Period-end dates represent only the reported month/quarter; they do not invent an exact operation date. Source estimates are labelled and not treated as confirmed future opening dates.
Colbún’s March 21, 2025 inauguration release gives approximately US$900 million investment and 816 MW installed output; its introductory text describes investment above US$900 million, so this is an approximate rounded figure. Expected annual generation is 2,450 GWh. The proposed 180 MW expansion and its separate US$200 million budget are excluded. Horizonte wind farm — original 816 MW: published generating capacity 816 MW. Operator-reported electric generating capacity; not annual energy production[1]
Colbún’s October 29, 2025 Q3 report confirms 100% commercial operation of the original 816 MW wind farm during Q3 2025.[1]
Something missing or wrong? Say it in your own words: a link that backs this pin up, a different start or end date and why, or a fact it lacks or gets wrong. The AI checks it against this pin's sources, searches for better ones, and adds any page that backs you up. The pin's own sources still count most. A picture that shows something else, or shows it badly, is looked at too, and moved down or replaced.
816 MW original wind project; 2,450 GWh/year published expected production is not measured annual generation.
Full commercial operation reported for Q3 2025 in the October results release.
“tercer trimestre de 2025”
Full commercial operation reported
“entrada en operación comercial del 100%”
Colbun says Horizonte supports Chile's move to a cleaner energy mix, decarbonization and energy security, and supplies renewable power to northern mining.
How: An 816 MW wind farm in Taltal, Antofagasta, expected to produce about 2,450 GWh a year.
For: About 715,000 homes' worth of electricity; mining customers; Taltal workers and suppliers.
Colbún’s March 21, 2025 inauguration release gives approximately US$900 million investment and 816 MW installed output; its introductory text describes investment above US$900 million, so this is an approximate rounded figure. Expected annual generation is 2,450 GWh. The proposed 180 MW expansion and its separate US$200 million budget are excluded.[2][3]
Colbún’s March 21, 2025 inauguration release gives approximately US$900 million investment and 816 MW installed output; its introductory text describes investment above US$900 million, so this is an approximate rounded figure. Expected annual generation is 2,450 GWh. The proposed 180 MW expansion and its separate US$200 million budget are excluded. Horizonte wind farm — original 816 MW: published generating capacity 816 MW. Operator-reported electric generating capacity; not annual energy production[2]
Colbún’s October 29, 2025 Q3 report confirms 100% commercial operation of the original 816 MW wind farm during Q3 2025.[3]
Retained only with documented physical construction, commissioning or 2025–2026 opening and published project-specific costs and electrical output. Costs use the published scope and currency; no benchmark estimates or currency conversions. MW is power capacity, not annual electricity production. Expected annual energy, where given, is a forecast. The map point is a reported plant/project location and may be approximate. Matching inventory views and excluded expansion proposals are not additive capacity.
Speaker at Horizonte’s March 21, 2025 inauguration, with wind turbines in the background. Colbún’s original project is rated 816 MW; the person’s identity is not inferred from the photograph. Credit: Colbún; photographer not named on source page. Operator source page; original image.
Power generation816 MW · Status: production. 816 MW original wind project; 2,450 GWh/year published expected production is not measured annual generation. Expected 2,450 GWh/year original-project output; not measured. Full commercial operation reported for Q3 2025 in the October results release. · source