EnBW’s September 17, 2026 inauguration release publishes approximately €2.4 billion investment and 960 MW installed output. All 64 turbines are built; commissioning is proceeding in stages and full commissioning is expected in the following months. Inauguration is not a claim of complete commercial operation. Published project rating: 960 MW. Operator-reported electric generating capacity; not annual energy production
Something missing or wrong? Say it in your own words: a link that backs this pin up, a different start or end date and why, or a fact it lacks or gets wrong. The AI checks it against this pin's sources, searches for better ones, and adds any page that backs you up. The pin's own sources still count most. A picture that shows something else, or shows it badly, is looked at too, and moved down or replaced.
EnBW’s September 17, 2026 inauguration release publishes approximately €2.4 billion investment and 960 MW installed output. All 64 turbines are built; commissioning is proceeding in stages and full commissioning is expected in the following months. Inauguration is not a claim of complete commercial operation.[2]
EnBW’s September 17, 2026 inauguration release publishes approximately €2.4 billion investment and 960 MW installed output. All 64 turbines are built; commissioning is proceeding in stages and full commissioning is expected in the following months. Inauguration is not a claim of complete commercial operation. Published project rating: 960 MW. Operator-reported electric generating capacity; not annual energy production[2]
Retained only with documented physical construction, commissioning or 2025–2026 opening and published project-specific costs and electrical output. Costs use the published scope and currency; no benchmark estimates or currency conversions. MW is power capacity, not annual electricity production. Expected annual energy, where given, is a forecast. The map point is a reported plant/project location and may be approximate. Matching inventory views and excluded expansion proposals are not additive capacity.