Dieppe–Le Tréport offshore substation installation image, from the project’s July 2025 installation gallery.[1]
Ocean Winds April 27, 2023 identifies €2.7 billion total investment specifically for Dieppe–Le Tréport, separately from the €7.4 billion three-project portfolio. Its approximately 500 MW rounded rating corresponds to the 496 MW inventory project. The release confirms transition into construction after investment decision; the August 2026 inventory still records construction.
Published project rating: 496 MW. 496 MW inventory rating; operator rounds project to approximately 500 MW[1]
Project partner confirms construction to start May 2023 after financing; the EUR2.4 billion financing is separate from total investment.[1]
Something missing or wrong? Say it in your own words: a link that backs this pin up, a different start or end date and why, or a fact it lacks or gets wrong. The AI checks it against this pin's sources, searches for better ones, and adds any page that backs you up. The pin's own sources still count most. A picture that shows something else, or shows it badly, is looked at too, and moved down or replaced.
Ocean Winds April 27, 2023 identifies €2.7 billion total investment specifically for Dieppe–Le Tréport, separately from the €7.4 billion three-project portfolio. Its approximately 500 MW rounded rating corresponds to the 496 MW inventory project. The release confirms transition into construction after investment decision; the August 2026 inventory still records construction.[1][3][5]
Ocean Winds April 27, 2023 identifies €2.7 billion total investment specifically for Dieppe–Le Tréport, separately from the €7.4 billion three-project portfolio. Its approximately 500 MW rounded rating corresponds to the 496 MW inventory project. The release confirms transition into construction after investment decision; the August 2026 inventory still records construction.[3]
Published project rating: 496 MW. 496 MW inventory rating; operator rounds project to approximately 500 MW[1]
Project partner confirms construction to start May 2023 after financing; the EUR2.4 billion financing is separate from total investment.[5]
Retained only with documented physical construction, commissioning or 2025–2026 opening and published project-specific costs and electrical output. Costs use the published scope and currency; no benchmark estimates or currency conversions. MW is power capacity, not annual electricity production. Expected annual energy, where given, is a forecast. The map point is a reported plant/project location and may be approximate. Matching inventory views and excluded expansion proposals are not additive capacity.
Dieppe–Le Tréport offshore substation installation image, from the project’s July 2025 installation gallery. Credit: EMDT / Christophe Beyssier. Source and gallery; original media.
Dieppe–Le Tréport offshore substation installation image, from the project’s July 2025 installation gallery. Credit: EMDT / Christophe Beyssier. Source and gallery; original media.