The first entry is always the pin's source. Overall confidence is a weighted average of how firmly each reference supports the start and end times used above; a reference counts half as much for every 180 days older than the newest.
Pin date 2025-08 matches the Aug 20, 2025 land-sale vote, the first sourced milestone for this site. No construction start or completion target is published.
Cited in the project timeline.[1]
Cited in the project timeline.[1]
Cited in the project timeline.[1]
Cited in the project timeline.[1]
Something missing or wrong? Say it in your own words: a link that backs this pin up, a different start or end date and why, or a fact it lacks or gets wrong. The AI checks it against this pin's sources, searches for better ones, and adds any page that backs you up. The pin's own sources still count most. A picture that shows something else, or shows it badly, is looked at too, and moved down or replaced.
228 acres
“closure comes as the community grapples with what will replace the 228-acre property”
$11.7M due within 30 days of when earthwork begins (no start date published)
“$11.7M will be due within 30 days of when earthwork begins.”
Land sold; course closed 2026-10-12; plan submitted to township, not yet presented to planning commission as of 2026-10-05
“That plan, submitted to Swatara Township but not yet presented to the township's planning commission”
Township votes 3-2 to rezone select properties to Mixed Use District allowing data centers
“initially voted 3-2 in April 2025 to rezone select properties to a Mixed Use District allowing data centers”
Dauphin County General Authority approves $45.6M sale to Harrisburg I, LLC (Provident Realty)
“The Dauphin County General Authority (DCGA) voted to execute a purchase with Harrisburg I, LLC to sell the Dauphin Highlands Golf Course.”
Authority lets buyer close early and lease the course back
“In May, the authority approved an amendment letting buyer Harrisburg I, LLC close early while leasing the course back”
Township approves community benefits agreements ($120.3M)
“Last week, the township approved the community benefits agreements”
Dauphin Highlands Golf Course closes
“Monday, October 12, is the course's final day of operation.”
Corscale Data Centers is planning Highlands West, a campus of three one-story buildings of 409,500 sq ft each on the 228-acre former Dauphin Highlands Golf Course in Swatara Township and Steelton, Dauphin County. The Dauphin County General Authority approved the $45.6 million sale to a Provident Realty entity on Aug. 20, 2025, and the course closed on Oct. 12, 2026. Swatara Township approved community benefits agreements worth $120.3 million in October 2026, while residents continue to raise noise, water and grid concerns. Corscale says it will spend $10.5 billion across Highlands West and the nearby Highlands East complex; no construction start or completion date is published.