The first entry is always the pin's source. Overall confidence is a weighted average of how firmly each reference supports the start and end times used above; a reference counts half as much for every 180 days older than the newest.
First dated milestone is the June 1, 2026 developer presentation; no groundbreaking or completion target is published. The pin's existing May 2026 start is not directly sourced (an April 2026 meeting is mentioned only in passing).
Cited in the project timeline.[1]
Hearing date and township meeting changes.[1]
Cited in the project timeline.[1]
Cited in the project timeline.[1]
1.54 million sq ft across six buildings
“The proposed development is a six-building, 1.54 million-square-foot data center complex covering about 245.5 acres of two parcels of land on either side of the Mifflin County Industrial Park.”
About 245.5 acres (two parcels either side of the Mifflin County Industrial Park)
“The proposed development is a six-building, 1.54 million-square-foot data center complex covering about 245.5 acres of two parcels of land on either side of the Mifflin County Industrial Park.”
Proposed: application rejected as incomplete; developer appeal heard Oct. 26, 2026, decision pending
“The zoning hearing board is expected to reconvene in January to deliberate and consider a decision on the appeal.”
Developer presentation to officials and public at township meeting
“The 16-page presentation, prepared by Pennsylvania Data Center Partners and PowerHouse Data Centers, describes a proposed data center development in Granville Township”
Land development plan filed with the township
“because developers submitted plans July 10, before the ordinance was adopted”
Township adopts data center ordinance (does not apply to the pending plan)
“township supervisors approved a data center ordinance that will not apply to the project currently under review”
Supervisors reject the application: missing traffic-study certification
“The Granville Township Board of Supervisors rejected an application for a data center in the area, citing a missing certification that was required as part of a traffic study.”
Developer appeals the rejection to the Zoning Hearing Board
“The Cumberland County-based development firm filed the appeal last month”
Zoning Hearing Board hearing postponed to a larger venue
“A zoning hearing regarding a data center developer's appeal was postponed Thursday after a sizable crowd turned out.”
Zoning Hearing Board hears the appeal (about 150 residents); briefs to follow
“Following testimony, the parties agreed to submit legal briefs outlining their respective arguments.”
Zoning Hearing Board expected to reconvene to decide the appeal
“The zoning hearing board is expected to reconvene in January to deliberate and consider a decision on the appeal.”
Something missing or wrong? Say it in your own words: a link that backs this pin up, a different start or end date and why, or a fact it lacks or gets wrong. The AI checks it against this pin's sources, searches for better ones, and adds any page that backs you up. The pin's own sources still count most. A picture that shows something else, or shows it badly, is looked at too, and moved down or replaced.
PA Data Center Partners (with PowerHouse Data Centers) proposes a six-building, 1.54 million-square-foot data center campus on about 245.5 acres of farmland off Loop Road in Granville Township, Mifflin County. The developers claim about 150 permanent jobs and $22.5 million a year in tax revenue but have published no power load, cost or schedule. Supervisors rejected the July 2026 application as incomplete, and the developer's appeal was heard by the Zoning Hearing Board on Oct. 26, 2026, with a decision expected after January 2027. Residents have turned out in large numbers against the project.