The first entry is always the pin's source. Overall confidence is a weighted average of how firmly each reference supports the start and end times used above; a reference counts half as much for every 180 days older than the newest.
The saved date is an estimated tracking or capacity-trajectory marker, not a verified exact opening day. Construction status follows the cited dated physical scope; no completion is inferred from elapsed targets.
Construction research 2026-10-24: Epoch’s[1] 2026-07-23 observation documents remaining physical construction/installation for this named buildout. In Progress does not complete earlier operating buildings or future capacity. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget. Source quote: “backup generators on the east side of the building still being installed” Dated observation 2026-07-23; future trajectory rows and modeled costs are distinguished from this physical milestone.
Something missing or wrong? Say it in your own words: a link that backs this pin up, a different start or end date and why, or a fact it lacks or gets wrong. The AI checks it against this pin's sources, searches for better ones, and adds any page that backs you up. The pin's own sources still count most. A picture that shows something else, or shows it badly, is looked at too, and moved down or replaced.
| 2026-10-31 | Building 2 (AKA CB4) is operational. On February 26, Terawulf [stated](https://investors.terawulf.com/news-events/press-releases/detail/132/terawulf-reports-fourth-quarter-and-full-year-2025-results) |
|---|
| 2027-03-31 | Building 3 (AKA CB5) is operational. On February 26, 2026, Terawulf [stated](https://investors.terawulf.com/news-events/press-releases/detail/132/terawulf-reports-fourth-quarter-and-full-year-2025-res |
|---|
Epoch AI satellite-imagery notes, in date order. · source
Physical-stage observation dated 2026-07-23. Campus buildout remains under construction; already operating buildings do not complete the remaining work. Forecast operational dates retain the directory’s uncertainty and do not establish actual completion.
“backup generators on the east side of the building still being installed”
Epoch’s dated 2026-07-23 assessment: backup generators on the east side of the building still being installed Campus buildout remains under construction; already operating buildings do not complete the remaining work.
“backup generators on the east side of the building still being installed”
Epoch estimates AI hardware: Google TPU v7 chips. Chip fit-out is directory research, not operator-certified inventory.
“We estimate that it uses Google TPU v7 chips.”
Epoch dated observation: Land clearing begins for Building 1 (AKA CB3).
“Land clearing begins for Building 1 (AKA CB3).”
Epoch assessment: Building 1 looks complete, consistent with it going operational back in May.
“Building 1 looks complete, consistent with it going operational back in May.”
Anthropic Lake Mariner in Barker, New York, United States is a frontier AI data center campus operated by AI XPV Platform / Anthropic reaching 378 MW of power capacity and 527,084 H100-equivalent AI accelerators. Built at a former coal plant on the shores of Lake Ontario, the Fluidstack-leased buildings are reported to serve Google TPUs for Anthropic.
Epoch’s 2026-07-23 observation documents remaining physical construction/installation for this named buildout. In Progress does not complete earlier operating buildings or future capacity. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget.