Construction research 2026-10-24: Epoch’s[1] 2026-09-05 observation documents remaining physical construction/installation for this named buildout. In Progress does not complete earlier operating buildings or future capacity. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget. Source quote: “Land clearing begins for Building 4.” Dated observation 2026-09-05; future trajectory rows and modeled costs are distinguished from this physical milestone.
Something missing or wrong? Say it in your own words: a link that backs this pin up, a different start or end date and why, or a fact it lacks or gets wrong. The AI checks it against this pin's sources, searches for better ones, and adds any page that backs you up. The pin's own sources still count most. A picture that shows something else, or shows it badly, is looked at too, and moved down or replaced.
| Building 1 expected to be fully operational, assuming a 3-month fit-out period |
| 2027-07-01 | Building 2 expected to be fully operational, assuming a 3-month fitout period after taking one year from land clearing to commissioning, as demonstrated by Building 1. Similarly. Building 3 is expecte |
|---|
| 2027-12-01 | Building 4 expected to be fully operational, assuming a 3-month fitout period after taking one year from land clearing to commissioning as demonstrated by Building 1. |
|---|
Epoch AI satellite-imagery notes, in date order. · source
Physical-stage observation dated 2026-09-05. Campus buildout remains under construction; already operating buildings do not complete the remaining work. Forecast operational dates retain the directory’s uncertainty and do not establish actual completion.
“Land clearing begins for Building 4.”
Epoch’s dated 2026-09-05 assessment: Land clearing begins for Building 4. Campus buildout remains under construction; already operating buildings do not complete the remaining work.
“Land clearing begins for Building 4.”
AI data-center compute infrastructure. Hardware inventory remains unpublished or not verified in this project assessment.
“AI data center”
Epoch dated observation: Land clearing begins for Building 1.
“Land clearing begins for Building 1.”
Epoch dated observation: Land clearing begins for Building 4.
“Land clearing begins for Building 4.”
Envision Galaxy Ulanqab in Ulanqab, Inner Mongolia , China is a frontier AI data center campus operated by Hyperscale AI Operator reaching 470 MW of power capacity and 169,869 H100-equivalent AI accelerators. Envision has stated this data center is built for large-scale model training. The first building is reportedly allocated to major Chinese tech companies, while subsequent buildings may be allocated to startups working on large model training.
Epoch’s 2026-09-05 observation documents remaining physical construction/installation for this named buildout. In Progress does not complete earlier operating buildings or future capacity. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget.