Construction research 2026-10-24: Epoch’s[1] 2026-03-12 observation documents remaining physical construction/installation for this named buildout. In Progress does not complete earlier operating buildings or future capacity. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget. Source quote: “Groundwork is visible for Building 1” Dated observation 2026-03-12; future trajectory rows and modeled costs are distinguished from this physical milestone.
Same Saline Township Stargate campus as pin 3444.[1]
Something missing or wrong? Say it in your own words: a link that backs this pin up, a different start or end date and why, or a fact it lacks or gets wrong. The AI checks it against this pin's sources, searches for better ones, and adds any page that backs you up. The pin's own sources still count most. A picture that shows something else, or shows it badly, is looked at too, and moved down or replaced.
Epoch AI satellite-imagery notes, in date order. · source
Physical-stage observation dated 2026-03-12. Campus buildout remains under construction; already operating buildings do not complete the remaining work. Forecast operational dates retain the directory’s uncertainty and do not establish actual completion.
“Groundwork is visible for Building 1”
Epoch’s dated 2026-03-12 assessment: Groundwork is visible for Building 1 Campus buildout remains under construction; already operating buildings do not complete the remaining work.
“Groundwork is visible for Building 1”
AI data-center compute infrastructure. Hardware inventory remains unpublished or not verified in this project assessment.
“AI data center”
Epoch dated observation: Land clearing begins for the entire site
“Land clearing begins for the entire site”
Epoch dated observation: Groundwork is visible for Building 1, at the left end of the site.
“Groundwork is visible for Building 1, at the left end of the site.”
Epoch’s 2026-03-12 observation documents remaining physical construction/installation for this named buildout. In Progress does not complete earlier operating buildings or future capacity. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget.
Hyperscale frontier AI training and inference campus tracked by Epoch AI with annotated satellite footprints (2 physical parts).