The saved date is an estimated tracking or capacity-trajectory marker, not a verified exact opening day. Construction status follows the cited dated physical scope; no completion is inferred from elapsed targets.
Construction research 2026-10-24: Epoch’s[1] 2026-06-13 observation documents remaining physical construction/installation for this named buildout. In Progress does not complete earlier operating buildings or future capacity. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget. Source quote: “all the yard work directly surrounding it” Dated observation 2026-06-13; future trajectory rows and modeled costs are distinguished from this physical milestone.
Something missing or wrong? Say it in your own words: a link that backs this pin up, a different start or end date and why, or a fact it lacks or gets wrong. The AI checks it against this pin's sources, searches for better ones, and adds any page that backs you up. The pin's own sources still count most. A picture that shows something else, or shows it badly, is looked at too, and moved down or replaced.
| Estimating building 1 is operational by the end of the year, judging from the building currently completed, the completed power substation to the southwest. The surrounding yard work/construction will |
| 2027-12-31 | Core Scientific expects initial delivery of the second, unleased 82.5 MW Muskogee building in Q4 2027. Not signed to have CoreWeave GPUs as of yet, but may change in the future. Source: https://www.se |
|---|
Epoch AI satellite-imagery notes, in date order. · source
Physical-stage observation dated 2026-06-13. Campus buildout remains under construction; already operating buildings do not complete the remaining work. Forecast operational dates retain the directory’s uncertainty and do not establish actual completion.
“all the yard work directly surrounding it”
Epoch’s dated 2026-06-13 assessment: all the yard work directly surrounding it Campus buildout remains under construction; already operating buildings do not complete the remaining work.
“all the yard work directly surrounding it”
AI data-center compute infrastructure. Hardware inventory remains unpublished or not verified in this project assessment.
“AI data center”
Epoch dated observation: Core Scientific, CoreWeave, and Port Muskogee publicly announce…
“Core Scientific, CoreWeave, and Port Muskogee publicly announce groundbreaking for the 100 MW Muskogee HPC data center.”
Epoch assessment: Based on satellite imagery, Building 1 has completed construction, with…
“Based on satellite imagery, Building 1 has completed construction, with adjacent land cleared for what we're assuming will have power substations/generators.”
Epoch’s 2026-06-13 observation documents remaining physical construction/installation for this named buildout. In Progress does not complete earlier operating buildings or future capacity. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget.
Hyperscale frontier AI training and inference campus tracked by Epoch AI with annotated satellite footprints (6 physical parts).