The first entry is always the pin's source. Overall confidence is a weighted average of how firmly each reference supports the start and end times used above; a reference counts half as much for every 180 days older than the newest.
The saved date is an estimated tracking or capacity-trajectory marker, not a verified exact opening day. Construction status follows the cited dated physical scope; no completion is inferred from elapsed targets.
Construction research 2026-10-24: Epoch’s[1] 2026-02-13 observation documents remaining physical construction/installation for this named buildout. In Progress does not complete earlier operating buildings or future capacity. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget. Source quote: “only a few backup generators” Dated observation 2026-02-13; future trajectory rows and modeled costs are distinguished from this physical milestone.
Something missing or wrong? Say it in your own words: a link that backs this pin up, a different start or end date and why, or a fact it lacks or gets wrong. The AI checks it against this pin's sources, searches for better ones, and adds any page that backs you up. The pin's own sources still count most. A picture that shows something else, or shows it badly, is looked at too, and moved down or replaced.
| 2026-02-13 |
|---|
| Building 1 is operational, based on the substation being completed earlier and cars in the carpark. Building 2 and 3 are not operational, based on minor construction work at the perimeter and no cars |
| 2026-05-14 | Building 2 and 3 are operational, based on the previous entry. |
|---|
| 2027-02-13 | Building 4 and 5 are operational, based on Building 5 being roughly 1 year behind Building 1 in satellite imagery. |
|---|
Epoch AI satellite-imagery notes, in date order. · source
Physical-stage observation dated 2026-02-13. Campus buildout remains under construction; already operating buildings do not complete the remaining work. Forecast operational dates retain the directory’s uncertainty and do not establish actual completion.
“only a few backup generators”
Epoch’s dated 2026-02-13 assessment: only a few backup generators Campus buildout remains under construction; already operating buildings do not complete the remaining work.
“only a few backup generators”
AI data-center compute infrastructure. Hardware inventory remains unpublished or not verified in this project assessment.
“AI data center”
Epoch dated observation: Land clearing begins.
“Land clearing begins.”
Epoch dated observation: Building 1 is operational, based on the substation being completed…
“Building 1 is operational, based on the substation being completed earlier and cars in the carpark.”
Epoch dated observation: Building 2 and 3 are operational, based on the previous entry.
“Building 2 and 3 are operational, based on the previous entry.”
Epoch’s 2026-02-13 observation documents remaining physical construction/installation for this named buildout. In Progress does not complete earlier operating buildings or future capacity. Power and accelerator counts remain Epoch estimates, not an operator-certified rating. Modeled 2025-dollar capital costs include compute hardware and are not a source-native construction budget.
Hyperscale frontier AI training and inference campus tracked by Epoch AI with annotated satellite footprints (16 physical parts).