The first entry is always the pin's source. Overall confidence is a weighted average of how firmly each reference supports the start and end times used above; a reference counts half as much for every 180 days older than the newest.
The source explicitly dates this event.
Overall completed restart safety programme, not incremental expenditure on this startup/grid milestone. Restart safety-measures opportunity cost including shared station safety facilities; excludes separately planned later anti-terrorism facilities. Exact quote: “approximately 570 billion yen”.[1]
Something missing or wrong? Say it in your own words: a link that backs this pin up, a different start or end date and why, or a fact it lacks or gets wrong. The AI checks it against this pin's sources, searches for better ones, and adds any page that backs you up. The pin's own sources still count most. A picture that shows something else, or shows it badly, is looked at too, and moved down or replaced.
Power generation and grid connection resume at 18:00 Japan time; commercial service remains a later milestone.[1]
796 MW electrical capacity. Historical generating capacity; not a claim about current output.[2]
Project cost: JPY 570,000,000,000. Overall completed restart safety programme, not incremental expenditure on this startup/grid milestone. Restart safety-measures opportunity cost including shared station safety facilities; excludes separately planned later anti-terrorism facilities. Source quote: “approximately 570 billion yen”. Stated currency; no foreign-exchange or inflation conversion.[3]
Photo: Kyodo News via AP / China Daily. Onagawa station, October 24, 2024; Kyodo News via AP, published by China Daily November 16. Station context, not a photograph of each dated milestone. Source and credit.
Power generation796 MW · 796 MW electrical capacity. Historical generating capacity; not a claim about current output. · source