August 2026 inspection targets December 2027 completion. December 31 is a month-precision anchor, not an announced opening day.
Opened primary project source for sourced buildout metrics and project timeline; researched 2026-10-29.[1]
Construction research 2026-10-24: Cablebús Line 4 is In Progress: the August 23, 2026 inspection reports 20% physical progress and expected December 2027 completion. The government’s allocation is more than MXN4.7bn for this line; price and lower bound preserve that threshold. Existing Cablebús services and completed studies do not complete the new Tlalpan–Coyoacán route. December 31 remains an estimated month anchor. Source quote: “20 por ciento de avance”[1]
Construction research 2026-10-24: Cablebús Line 4 is In Progress: the August 23, 2026 inspection reports 20% physical progress and expected December 2027 completion. The government’s allocation is more than MXN4.7bn for this line; price and lower bound preserve that threshold. Existing Cablebús services and completed studies do not complete the new Tlalpan–Coyoacán route. December 31 remains an estimated month anchor. Source quote: “4 mil 700 millones de pesos”[1]
Something missing or wrong? Say it in your own words: a link that backs this pin up, a different start or end date and why, or a fact it lacks or gets wrong. The AI checks it against this pin's sources, searches for better ones, and adds any page that backs you up. The pin's own sources still count most. A picture that shows something else, or shows it badly, is looked at too, and moved down or replaced.
11 km, nine stations and 390 cabins.
“9 estaciones, son 11 kilómetros, son 390 cabinas”
Construction forecast to conclude end-2027; site inspection reports work underway.
“concluir la obra a finales del 2027”
Construction completion forecast
“concluir la obra a finales del 2027”
Residents of Tlalpan, Coyoacán and Cantera, including university students, face long trips to Ciudad Universitaria; the Mexican president calls the Cablebús a social-justice project dedicated to those with the least.
How: Cablebús Line 4 (11.4 km, nine stations) cuts the trip to about 40 minutes, half the current travel time, and connects with parks and Utopías.
For: University students in Tlalpan, Coyoacán and Cantera; designed for 65,000 passengers and potentially more than 155,000 residents of 44 neighborhoods.
Cablebús Line 4 is In Progress: the August 23, 2026 inspection reports 20% physical progress and expected December 2027 completion. The government’s allocation is more than MXN4.7bn for this line; price and lower bound preserve that threshold. Existing Cablebús services and completed studies do not complete the new Tlalpan–Coyoacán route. December 31 remains an estimated month anchor.