ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 4 references, the source included, support the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
August 2026 inspection targets December 2027 completion. December 31 is a month-precision anchor, not an announced opening day.[1]The 11.4-kilometre cable car will run nine stations from Pedregal de San Nicolás in the Ajusco down to Metro Universidad, carrying an investment the presidency puts at "más de 4 mil 700 millones de pesos" (more than 4.7 billion pesos). Construction stood at 20 per cent when President Sheinbaum inspected the works in August 2026.