Stated as fact, per the MBTA[6] release posted 4 September 2026: "Governor Maura Healey today joined ... to break ground on the North Station Draw One Bridge Replacement Project".
Wikipedia's bridge article: the $1.06 billion design-build contract to Skanska Civil Northeast/Koch JV and notice to proceed in May 2026, groundbreaking in September 2026.
STV (project engineer) on the $1.286 billion project: two new three-track bridges built so four tracks stay open, 80 switches, 10 miles of track, 12 tracks and six platforms.[1]
AASHTO Journal on the groundbreaking: $1.2 billion project, $472.3 million MEGA grant, completion expected in fall 2032.[1]
Trade coverage of the ceremonial groundbreaking: six-track vertical lift bridges, 10 to 12 station tracks, completion expected fall 2032.[1]
Something missing or wrong? Say it in your own words: a link that backs this pin up, a different start or end date and why, or a fact it lacks or gets wrong. The AI checks it against this pin's sources, searches for better ones, and adds any page that backs you up. The pin's own sources still count most.