Season only, per the MBTA[5] project page: "Anticipated project completion: Fall 2032" - taken as the last day of fall 2032.
Wikipedia: 2026-2034 construction in the 2024 environmental assessment; at groundbreaking the $1.286 billion project was expected to be complete in late 2032.
STV: anticipated completion in 2032, two three-track bridges, 80 switches, 10 miles of track.[1]
AASHTO Journal repeats MassDOT's fall 2032 completion and the shortened schedule.[1]
The MBTA's[1] groundbreaking release: 'completion expected in fall 2032' after cutting the timeline from eight years to about six and a half.
Something missing or wrong? Say it in your own words: a link that backs this pin up, a different start or end date and why, or a fact it lacks or gets wrong. The AI checks it against this pin's sources, searches for better ones, and adds any page that backs you up. The pin's own sources still count most.