The City of Beverly Hills says Section 2 "is under construction and scheduled for completion in Spring 2027", and Metro's[2][4] September 2026 schedule gives Section 2 operations as "Spring 2027"; a season takes its last day.
Metro's[4] fact sheet: Section 2 is 2.59 miles with Beverly Dr and Century City stations, operations Spring 2027; life-of-project budget for all three sections $9.7 billion.
Section 2 groundbreaking February 23, 2018; tunneling completed April 2, 2024; Section 1 opened May 8, 2026; Sections 2 and 3 listed for 2027.[1]
Metro's[2] forecasted schedule table: Section 2 construction 2018-2026, operations Spring 2027; Section 3 operations Fall 2027; Section 1 opened May 8, 2026.
Photos of Beverly Drive station (Wilshire at Reeves) and Century City station (Constellation and Avenue of the Stars) with escalators and roof structures in place.[1]
Something missing or wrong? Say it in your own words: a link that backs this pin up, a different start or end date and why, or a fact it lacks or gets wrong. The AI checks it against this pin's sources, searches for better ones, and adds any page that backs you up. The pin's own sources still count most.