The first entry is always the pin's source. Overall confidence is a weighted average of how firmly each reference supports the start and end times used above; a reference counts half as much for every 180 days older than the newest.
Only the quarter is supported. 2029-03-31 is a timeline anchor, not a confirmed operating day. The operator retains a Q1 2029 target, conditional on NRC approval. March 31 is a quarter-end timeline anchor, not a scheduled startup day.
Operator anticipates full operation by first quarter 2029, conditional on approvals.[1]
NextEra’s September 8, 2026 release confirms an up-to-$1.9 billion DOE loan for Duane Arnold’s restart. The operator targets no later than Q1 2029, pending approvals. This is restoration of the retired Iowa reactor, not a newly built nuclear unit.[1]
Same project/site; inventory records are an additional source view, not additive capacity on top of existing pin figures.[1]
Independent account of the loan close.[1]
Something missing or wrong? Say it in your own words: a link that backs this pin up, a different start or end date and why, or a fact it lacks or gets wrong. The AI checks it against this pin's sources, searches for better ones, and adds any page that backs you up. The pin's own sources still count most. A picture that shows something else, or shows it badly, is looked at too, and moved down or replaced.
The operator retains a Q1 2029 target, conditional on NRC approval. March 31 is a quarter-end timeline anchor, not a scheduled startup day.[2]
615 MW electrical capacity. Proposed 615 MW electrical generation; retired since 2020 and not yet restarted as of October 24, 2026.[7]
Cost: not assigned. No event-specific published construction/restart budget was verified. Financing, damages and other phases are not substituted.
Only the quarter is supported. 2029-03-31 is a timeline anchor, not a confirmed operating day. The operator retains a Q1 2029 target, conditional on NRC approval. March 31 is a quarter-end timeline anchor, not a scheduled startup day.
Photo: NextEra Energy. Duane Arnold Energy Center on a sunny day, from the operator’s official project page. Undated site context, not a photograph of every historical milestone. Source and credit.
Power generation615 MW · 615 MW electrical capacity. Proposed 615 MW electrical generation; retired since 2020 and not yet restarted as of October 24, 2026. · source