A target, per the source: "Phase 1 of the Cross Island Line is scheduled to open in 2030."
Land Transport Guru gives Phase 1 as "(2030)" and records that it was first "slated to open by 2029" before an LTA[4] press release in March 2021 pushed it to 2030 over COVID-19 supply and manpower disruptions; an enthusiast site, though it cites LTA throughout.
Wikipedia lists Phase 1's start date as 2030 and its 12 stations as "under construction, to be ready by 2030", citing LTA[4]; a well-sourced summary rather than an official statement.
LTA's own project page, last updated 4 August 2026, says "CRL1 is expected to be completed by 2030" and that construction "is progressing well" - the operator's current target, but a year rather than a day.
Something missing or wrong? Say it in your own words: a link that backs this pin up, a different start or end date and why, or a fact it lacks or gets wrong. The AI checks it against this pin's sources, searches for better ones, and adds any page that backs you up. The pin's own sources still count most.