The first entry is always the pin's source. Overall confidence is a weighted average of how firmly each reference supports the start and end times used above; a reference counts half as much for every 180 days older than the newest.
Pin date 2025-05-13 is the Pennrose[5] announcement; the ribbon cutting was May 12, 2025 and first residents moved in April 2025. Delivery targets were early 2025 (housing authority) and January 2025 (CRA).
Completion report: $17.6M, 85,765 sq ft, 981 Peach Ave., Capstone Building Corp.[1]
Government CRA release: total project cost exceeding $25M, $6M CRA loan, January 2025 target[1]
Cost benchmark: “Affordable LIHTC Variant $240k–$380k/unit 9% or 4% LIHTC.”[1]
Project-specific operator, government or project-partner source reviewed on October 9, 2026.[1]
Something missing or wrong? Say it in your own words: a link that backs this pin up, a different start or end date and why, or a fact it lacks or gets wrong. The AI checks it against this pin's sources, searches for better ones, and adds any page that backs you up. The pin's own sources still count most. A picture that shows something else, or shows it badly, is looked at too, and moved down or replaced.
99 affordable senior apartments
“a 99-unit, affordable senior housing development located within the mixed-income community in Memphis' Medical District.”
Affordable LIHTC variant, applied to Memphis, TN. Subsidized affordable project; stories not published so LIHTC row chosen over garden row.
“Affordable LIHTC Variant $240k–$380k/unit 9% or 4% LIHTC.”
Top of the same published range.
“Affordable LIHTC Variant $240k–$380k/unit 9% or 4% LIHTC.”
Low: 99 × $240,000 = $23,760,000. High: 99 × $380,000 = $37,620,000.
99 × $310,000 (midpoint per unit) = $30,690,000, rounded to $30.7 million. About $310,000 per unit.
Land, design and permit fees, financing and the developer fee are excluded, so this is a vertical building cost, not a project budget. The benchmark is a 2026 range with no adjustment for the year this was built. Stories and construction type unpublished; LIHTC row note says CA/NY/MA/IL near market-rate, so Memphis may fall low; excludes land, soft costs, financing. No construction budget was found for this project.
85,765 sq ft
“Construction has been completed on the $17.6 million Edgeview at Legends Park, an 85,765-square-foot senior-housing development”
99 affordable senior apartments
“a 99-unit, affordable senior housing development located within the mixed-income community in Memphis' Medical District.”
Groundbreaking December 2023; ribbon cutting May 12, 2025
“the 99-unit, 100% affordable senior housing facility celebrated its ribbon cutting”
Grand opening May 2025
“Memphis Housing Authority and Pennrose today announced the grand opening of Edgeview at Legends Park”
Groundbreaking announced (housing authority)
“today announced the groundbreaking of Edgeview at Legends Park, a 99-unit, senior affordable housing development”
First residents move in
“Washington said the building welcomed its first residents in April of this year.”
Ribbon cutting / grand opening
“the 99-unit, 100% affordable senior housing facility celebrated its ribbon cutting”
Grand opening announced May 13, 2025. Confirmed announced milestone: Grand opening announced May 13, 2025. The date records the stated ceremony or dated announcement; it does not imply current apartment availability.
Contact Memphis Housing Authority and management about the applicable voucher/referral route. The operator’s contact form expressly is not an application or pre-application and establishes no queue position.[1]
Dollar rents were not verified in the project-specific sources checked. Income limits do not establish a fixed monthly rent. Consult the linked property leasing information.
No construction budget was found for this project, so the price is an estimate built from published inputs, not a reported figure. The working:
Stated by the source · 99 affordable senior units; 85,765 sq ft.