The first entry is always the pin's source. Overall confidence is a weighted average of how firmly each reference supports the start and end times used above; a reference counts half as much for every 180 days older than the newest.
The pin's start of 30 Nov 2020 matches no published milestone: Phase I was completed in March 2021 (Duvernay + Brooks) and opened 14 July 2021; the full 300-home redevelopment was announced complete on 2 Nov 2023 (NY HCR).
Developer page for the Phase II grand opening; source of the ribbon-cutting photograph.[1]
Co-developer project page: Phase I completed March 2021 with a $29.7 million budget, Phase II $88 million, completed 2023.[1]
Project-specific operator, government or project-partner source reviewed on October 10, 2026.[1]
Project-specific operator, government or project-partner source reviewed on October 10, 2026.[1]
20 acres
“Built in 1948, the 300-unit Yates Village spans 20 acres and is the largest public housing development in the city.”
300 homes (89 in Phase I, 211 in Phase II)
“Governor Kathy Hochul today announced the completion Northside Village, an extensive public housing revitalization in Schenectady that now offers 300 modern, affordable, and energy-efficient homes”
Phase I demolition Sept 2019; Phase I done 2021; Phase II done 2023
“The second phase was completed in 2023 and converted to permanent financing in 2024.”
Completed (all 300 homes, announced 2 Nov 2023)
“Governor Kathy Hochul today announced the completion Northside Village, an extensive public housing revitalization in Schenectady that now offers 300 modern, affordable, and energy-efficient homes”
Phase I demolition begins
“Phase I demolition began in September 2019”
Phase I (89 apartments) completed
“was completed in March 2021, and converted to permanent financing in 2022”
Phase I grand opening
“Northside Village, the redeveloped portion of the Yates Village public housing complex, made its official debut Wednesday”
Phase II (211 apartments) construction start, as planned in July 2021
“Phase II is expected to begin in the fall of 2021 and includes the redevelopment of 211 affordable apartments.”
Phase II completed; all 300 homes announced complete
“Governor Kathy Hochul today announced the completion Northside Village, an extensive public housing revitalization in Schenectady that now offers 300 modern, affordable, and energy-efficient homes”
Something missing or wrong? Say it in your own words: a link that backs this pin up, a different start or end date and why, or a fact it lacks or gets wrong. The AI checks it against this pin's sources, searches for better ones, and adds any page that backs you up. The pin's own sources still count most. A picture that shows something else, or shows it badly, is looked at too, and moved down or replaced.
Yates Village, a public housing complex built in 1948, was 75 years old with outdated structures; its two-phase revitalization into Northside Village preserved and replaced it.
How: 300 modern, affordable, energy-efficient homes, including 61 units with supportive services; Phase II demolished six outdated structures and built 211 apartments, 43 of them supportive units.
For: Households at or below 80% of Area Median Income, including veterans and people with physical disabilities.
Developer records completion in November 2020. Estimated timeline boundary: Developer records completion in November 2020. The date represents the end of the published window, not an announced exact day; completion and move-in remain distinct.
Subsidized apartments require SMHA referrals. The operator requires a paper pre-application for other homes; its listed minimum income for a two-bedroom tax-credit home is $52,046. Leasing phone: 518.401.0661. Eligibility and application document.
Monthly prices shown on the operator’s current property page, checked October 10, 2026. Apartment and program eligibility vary.[1]
| Apartment / condition | Monthly rent |
|---|---|
| 1 bedroom — operator-listed | $1,266–$1,728 |
| 2 bedroom — operator-listed | $1,518–$2,072 |
| 3 bedroom — operator-listed | $1,767–$2,408 |
The page does not assign every rate to an income tier. Mixed-income ranges may include market-rate homes. Assisted residents may pay a different income-based contribution. Confirm utilities, fees, qualification and a final quote with leasing.
Eligibility: the linked operator documents identify a Low-Income Housing Tax Credit program. Qualification depends on household size and annual income; voucher and market-rate homes, where offered, use separate rules.
Stated by the source · 300 homes in total; Yates Village spans 20 acres.