Estimated: Milam County, Texas; approximate county context, exact solar parcel not establishedBen Milam Solar 5
ESTIMATEDDate confidence: ESTIMATEDA target, not a fixed dateHow firmly the source words the date: confirmed, scheduled, estimated, delayed or unverified.Show all ESTIMATED pins65% CONFIDENCEOverall confidence: 65%How well the pin's source and references back up its dates.Weighted average of how firmly 1 reference supports the pin's start and end times; a reference counts half as much for every 180 days older than the newestShow all pins from 50% to 74% confidence
November 12, 2026 is ERCOT’s[1] projected COD, not a confirmed delivery; FIS Started / No IA warrants schedule follow-up.ERCOT identifies Aquila Solar as Ben Milam Solar 5’s 500 MW solar request at Gibson Switch 345 kV in Milam County. Its requested commercial date is November 12, 2026; the queue shows screening complete, FIS started and no interconnection agreement.
1.00